Wichita Creek Solar, LLC
Wichita Creek Solar, LLC has 1 planned power project totaling 3.4 MW in the FieldProspects database and no operating project on record. 0% of the planned capacity has an interconnection agreement and 0% is past its listed in-service date. The projects sit in 1 state and 1 technology.
Where Wichita Creek Solar, LLC's planned pipeline sits
Planned MW by state. Everything sits in Texas.
Largest states
- Texas3.4 MW1 project, 100% of planned
and no operating project on record yet. Everything here is pipeline.
View as table
| Technology | Planned projects | Planned MW | Operating projects | Operating MW |
|---|---|---|---|---|
| Solar | 1 | 3.4 MW | 0 | 0 MW |
MW by technologySolar has no operating projects
How much of the pipeline is real
An interconnection agreement and a construction start are the two strongest signals that a queue project will be built. A listed date that has already passed is the strongest sign it will not be built on time.
Share of Wichita Creek Solar, LLC's planned MWSee the queue slip report
Planned MW by listed in-service year
Projects listed before 2026 and still planned are past due.
View as table
| Year | Projects | MW |
|---|---|---|
| 2026 | 0 | 0 MW |
| 2027 | 0 | 0 MW |
| 2028 | 1 | 3.4 MW |
Pipeline by grid and queue year
Wichita Creek Solar, LLC's planned MW sits entirely in ERCOT.
Planned MW by grid operator
1 planned project
View as table
| Grid | Planned projects | Planned MW |
|---|---|---|
| ERCOT | 1 | 3.4 MW |
When the planned projects entered the queue
Planned MW by queue request year. 2026 was the biggest year.
View as table
| Queue year | Projects | MW |
|---|---|---|
| 2026 | 1 | 3.4 MW |
Changes since the June 4, 2026 snapshot
What moved in Wichita Creek Solar, LLC's queue position between June 4, 2026 and October 8, 2026.
Which projects were added, finished, cancelled or shelved
| Change | Project | Technology | State | MW | Grid |
|---|---|---|---|---|---|
Members see each changed project with its name, location and dates, and get an email when Wichita Creek Solar, LLC's pipeline moves.
Wichita Creek Solar, LLC against the nine largest developers
The nine largest planned pipelines in the database, ranked by planned MW. NextEra Energy leads with 36.8 GW planned. Wichita Creek Solar, LLC ranks 777 of 815 developers with a planned project.
| # | Developer | Planned projects | Planned MW | Operating projects | Operating MW | Operating per planned |
|---|---|---|---|---|---|---|
| 1 | NextEra Energy | 191 | 75 | 0.32 | ||
| 2 | Invenergy | 135 | 28 | 0.17 | ||
| 3 | Intersect Power | 54 | 5 | 0.05 | ||
| 4 | Hecate Energy | 41 | 8 | 0.06 | ||
| 5 | Engie | 80 | 51 | 0.24 | ||
| 6 | RWE | 78 | 20 | 0.25 | ||
| 7 | Avantus | 49 | 10 | 0.14 | ||
| 8 | EDF Renewables | 54 | 15 | 0.12 | ||
| 9 | OCI Energy | 45 | 1 | 0.01 | ||
| 777 | Wichita Creek Solar, LLC this page | 1 | 0 | 0.00 |
Operating per planned is operating MW divided by planned MW. A low ratio means a pipeline far larger than the fleet already built.
Top 9 by planned MW, plus Wichita Creek Solar, LLCEvery Wichita Creek Solar, LLC project
The one project with name, county, grid, MW, queue date, in-service date, interconnection status and construction status. Filter, sort and export to Excel.
| Project | County | Grid | MW | Queue date | In service | Agreement |
|---|---|---|---|---|---|---|
Project names never appear next to their developer on public pages. Members see both.
Get alerts for Wichita Creek Solar, LLC
We email you when Wichita Creek Solar, LLC adds a project, signs an interconnection agreement, starts construction, slips a date or drops a project. One email per snapshot, only when something changed.
See every Wichita Creek Solar, LLC project, with its county, dates and queue status.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.