The queue slip report
161,870.5 MW of planned US power was due online before 2026 and still is not built.
1,079 projects in the seven ISO and RTO queues list an in-service year before 2026. By grid, year due, technology, state and developer.
Past-due MW as a share of each queue
Seven ISO and RTO queues, October 8, 2026
View as table
| Grid | Share of queue past due |
|---|---|
| MISO | 28.9% |
| PJM | 24.4% |
| CAISO | 3.3% |
| ERCOT | 0.6% |
| SPP | 1.6% |
| ISO-NE | 0.2% |
What changed in US power queues
Between June 4, 2026 and October 8, 2026: 882 projects cancelled (180,206.4 MW), 1,020 slipped their dates by a median of 182 days, 587 joined a queue.
County pages and developer profiles
Every county with power projects or data centers, and every developer with a pipeline, has a public page with the shape of the market. Members open the records behind each number.