Tesla
Tesla has 10 planned power projects totaling 337.4 MW and 15 operating projects totaling 389.4 MW in the FieldProspects database. 79% of the planned capacity has an interconnection agreement and 39% is past its listed in-service date. It also has 1 data center record.
Where Tesla's planned pipeline sits
Planned MW by state. The 3 largest states hold 337.4 MW of the 337.4 MW.
Largest states
- Texas332.6 MW5 projects, 99% of planned
- California3.8 MW4 projects, 1% of planned
- Nevada1 MW1 project, 0% of planned
for every MW Tesla operates today. Battery Storage is most of the gap.
View as table
| Technology | Planned projects | Planned MW | Operating projects | Operating MW |
|---|---|---|---|---|
| Battery Storage | 3 | 383.6 MW | 3 | 375 MW |
| Solar | 7 | -46.2 MW | 12 | 14.4 MW |
MW by technologyPlanned and operating MW
How much of the pipeline is real
An interconnection agreement and a construction start are the two strongest signals that a queue project will be built. A listed date that has already passed is the strongest sign it will not be built on time.
Share of Tesla's planned MWSee the queue slip report
Planned MW by listed in-service year
Projects listed before 2026 and still planned are past due.
View as table
| Year | Projects | MW |
|---|---|---|
| 2025 | 1 | 133 MW |
| 2026 | 7 | 132.4 MW |
| 2027 | 2 | 72 MW |
Pipeline by grid and queue year
Tesla's planned MW leans on ERCOT, California ISO (CAISO) and Nevada Power (NV Energy). ERCOT alone holds 99% of it.
Planned MW by grid operator
10 planned projects
View as table
| Grid | Planned projects | Planned MW |
|---|---|---|
| ERCOT | 5 | 332.6 MW |
| California ISO (CAISO) | 4 | 3.8 MW |
| Nevada Power (NV Energy) | 1 | 1 MW |
When the planned projects entered the queue
Planned MW by queue request year. 2024 was the biggest year.
View as table
| Queue year | Projects | MW |
|---|---|---|
| 2022 | 1 | -53.3 MW |
| 2023 | 1 | 125.3 MW |
| 2024 | 2 | 258.3 MW |
Changes since the June 4, 2026 snapshot
What moved in Tesla's queue position between June 4, 2026 and October 8, 2026.
Which projects were added, finished, cancelled or shelved
| Change | Project | Technology | State | MW | Grid |
|---|---|---|---|---|---|
Members see each changed project with its name, location and dates, and get an email when Tesla's pipeline moves.
Tesla against the nine largest developers
The nine largest planned pipelines in the database, ranked by planned MW. NextEra Energy leads with 36.8 GW planned. Tesla ranks 360 of 815 developers with a planned project.
| # | Developer | Planned projects | Planned MW | Operating projects | Operating MW | Operating per planned |
|---|---|---|---|---|---|---|
| 1 | NextEra Energy | 191 | 75 | 0.32 | ||
| 2 | Invenergy | 135 | 28 | 0.17 | ||
| 3 | Intersect Power | 54 | 5 | 0.05 | ||
| 4 | Hecate Energy | 41 | 8 | 0.06 | ||
| 5 | Engie | 80 | 51 | 0.24 | ||
| 6 | RWE | 78 | 20 | 0.25 | ||
| 7 | Avantus | 49 | 10 | 0.14 | ||
| 8 | EDF Renewables | 54 | 15 | 0.12 | ||
| 9 | OCI Energy | 45 | 1 | 0.01 | ||
| 360 | Tesla this page | 10 | 15 | 1.15 |
Operating per planned is operating MW divided by planned MW. A low ratio means a pipeline far larger than the fleet already built.
Top 9 by planned MW, plus TeslaEvery Tesla project
All 25 projects with name, county, grid, MW, queue date, in-service date, interconnection status and construction status. Filter, sort and export to Excel.
| Project | County | Grid | MW | Queue date | In service | Agreement |
|---|---|---|---|---|---|---|
Project names never appear next to their developer on public pages. Members see both.
Get alerts for Tesla
We email you when Tesla adds a project, signs an interconnection agreement, starts construction, slips a date or drops a project. One email per snapshot, only when something changed.
See every Tesla project, with its county, dates and queue status.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.