Leeward Energy
Leeward Energy has 55 planned power projects totaling 9.3 GW and 13 operating projects totaling 1.4 GW in the FieldProspects database. 70% of the planned capacity has an interconnection agreement and 3% is past its listed in-service date. 180 contacts at the company are on file.
Where Leeward Energy's planned pipeline sits
Planned MW by state. The 6 largest states hold 7.8 GW of the 9.3 GW.
for every MW Leeward Energy operates today. Solar is most of the gap.
View as table
| Technology | Planned projects | Planned MW | Operating projects | Operating MW |
|---|---|---|---|---|
| Solar | 32 | 5.6 GW | 8 | 1.1 GW |
| Battery Storage | 13 | 2.1 GW | 4 | 327 MW |
| Wind | 9 | 1.5 GW | 1 | 38 MW |
| Solar + Storage (Hybrid) | 1 | 200 MW | 0 | 0 MW |
MW by technologySolar + Storage (Hybrid) has no operating projects
How much of the pipeline is real
An interconnection agreement and a construction start are the two strongest signals that a queue project will be built. A listed date that has already passed is the strongest sign it will not be built on time.
Share of Leeward Energy's planned MWSee the queue slip report
Planned MW by listed in-service year
Projects listed before 2026 and still planned are past due.
View as table
| Year | Projects | MW |
|---|---|---|
| 2023 | 1 | 101.3 MW |
| 2024 | 2 | 10.3 MW |
| 2025 | 2 | 200 MW |
| 2026 | 13 | 2 GW |
| 2027 | 13 | 2 GW |
| 2028 | 12 | 2.7 GW |
| 2029 | 9 | 1.6 GW |
| 2030 | 3 | 650 MW |
Pipeline by grid and queue year
Leeward Energy's planned MW leans on PJM Interconnection, California ISO (CAISO) and ERCOT. PJM Interconnection alone holds 36% of it.
Planned MW by grid operator
55 planned projects
View as table
| Grid | Planned projects | Planned MW |
|---|---|---|
| PJM Interconnection | 20 | 3.3 GW |
| California ISO (CAISO) | 7 | 2.1 GW |
| ERCOT | 10 | 1.6 GW |
| Southwest Power Pool (SPP) | 10 | 1.5 GW |
| Midcontinent ISO (MISO) | 4 | 402.3 MW |
| Public Service Company of Colorado | 1 | 230 MW |
| PacifiCorp East | 2 | 116 MW |
| Tennessee Valley Authority | 1 | 50 MW |
When the planned projects entered the queue
Planned MW by queue request year. 2020 was the biggest year.
View as table
| Queue year | Projects | MW |
|---|---|---|
| 2014 | 2 | 400 MW |
| 2015 | 0 | 0 MW |
| 2016 | 0 | 0 MW |
| 2017 | 3 | 308.6 MW |
| 2018 | 1 | 3 MW |
| 2019 | 4 | 630 MW |
| 2020 | 13 | 2.1 GW |
| 2021 | 3 | 1.2 GW |
| 2022 | 2 | 380 MW |
| 2023 | 3 | 400 MW |
| 2024 | 1 | 200 MW |
| 2025 | 0 | 0 MW |
| 2026 | 2 | 500.3 MW |
Changes since the June 4, 2026 snapshot
What moved in Leeward Energy's queue position between June 4, 2026 and October 8, 2026.
Which projects were added, finished, cancelled or shelved
| Change | Project | Technology | State | MW | Grid |
|---|---|---|---|---|---|
Members see each changed project with its name, location and dates, and get an email when Leeward Energy's pipeline moves.
Leeward Energy against the nine largest developers
The nine largest planned pipelines in the database, ranked by planned MW. NextEra Energy leads with 36.8 GW planned. Leeward Energy ranks 13 of 815 developers with a planned project.
| # | Developer | Planned projects | Planned MW | Operating projects | Operating MW | Operating per planned |
|---|---|---|---|---|---|---|
| 1 | NextEra Energy | 191 | 75 | 0.32 | ||
| 2 | Invenergy | 135 | 28 | 0.17 | ||
| 3 | Intersect Power | 54 | 5 | 0.05 | ||
| 4 | Hecate Energy | 41 | 8 | 0.06 | ||
| 5 | Engie | 80 | 51 | 0.24 | ||
| 6 | RWE | 78 | 20 | 0.25 | ||
| 7 | Avantus | 49 | 10 | 0.14 | ||
| 8 | EDF Renewables | 54 | 15 | 0.12 | ||
| 9 | OCI Energy | 45 | 1 | 0.01 | ||
| 13 | Leeward Energy this page | 55 | 13 | 0.16 |
Operating per planned is operating MW divided by planned MW. A low ratio means a pipeline far larger than the fleet already built.
Top 9 by planned MW, plus Leeward Energy180 people at Leeward Energy
Contacts with title, seniority, department, email and LinkedIn, counted here and never named. 88 managers and 36 directors are where interconnection and procurement decisions start.
By seniority
180 contacts
View as table
| Seniority | Contacts |
|---|---|
| C-Suite | 7 |
| Head | 1 |
| VP | 12 |
| Director | 36 |
| Manager | 88 |
| Senior | 35 |
| Unknown | 1 |
Sample rows
Illustrative rows, names and details removed.
| Person | Title | Department | Seniority | Contact |
|---|---|---|---|---|
Names, titles, direct emails and LinkedIn profiles, matched to the projects they work on.
Every Leeward Energy project
All 68 projects with name, county, grid, MW, queue date, in-service date, interconnection status and construction status. Filter, sort and export to Excel.
| Project | County | Grid | MW | Queue date | In service | Agreement |
|---|---|---|---|---|---|---|
Project names never appear next to their developer on public pages. Members see both, plus the 180 contacts.
Get alerts for Leeward Energy
We email you when Leeward Energy adds a project, signs an interconnection agreement, starts construction, slips a date or drops a project. One email per snapshot, only when something changed.
See every Leeward Energy project and the 180 people behind them.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.