FieldProspects

Hexagon Energy

Power developer14 projects on record Data as of

Hexagon Energy has 14 planned power projects totaling 3.6 GW in the FieldProspects database and no operating project on record. 39% of the planned capacity has an interconnection agreement and 0% is past its listed in-service date. 16 contacts at the company are on file.

3.6GW
planned, 14 projects
0MW
operating, 0 projects
1.4GW
interconnection agreement signed, 39% of planned
0MW
under construction, 0 projects
0MW
past due, 0 projects
16
contacts on file
Map

Where Hexagon Energy's planned pipeline sits

Planned MW by state. The 4 largest states hold 3.6 GW of the 3.6 GW.

none planned under 250 MW250 to 1,000 MW1,000 to 2,500 MW2,500 to 5,000 MW5,000 MW or more

Largest states

  1. Illinois2.5 GW4 projects, 69% of planned
  2. Texas1 GW8 projects, 28% of planned
  3. Virginia138 MW1 project, 4% of planned
  4. New York2 MW1 project, 0% of planned
Source. ISO and RTO interconnection queues and EIA-860M, via FieldProspects Hover a state for its numbers
Planned against delivered
3.6 GWplanned

and no operating project on record yet. Everything here is pipeline.

PlannedOperating
Solar 2.6 GW
none
Battery Storage 1 GW
none
View as table
TechnologyPlanned projectsPlanned MWOperating projectsOperating MW
Solar62.6 GW00 MW
Battery Storage81 GW00 MW

MW by technologySolar and Battery Storage have no operating projects

How much of the pipeline is real

An interconnection agreement and a construction start are the two strongest signals that a queue project will be built. A listed date that has already passed is the strongest sign it will not be built on time.

Interconnection agreement signed1.4 GW, 39%
4 of 14 planned projects (29%)
Under construction0 MW, 0%
0 of 14 planned projects (0%)
Past due0 MW, 0%
0 of 14 planned projects (0%)
0% of Hexagon Energy's planned MW in the seven ISO queues is past due, against 11% for all developers.

Share of Hexagon Energy's planned MWSee the queue slip report

Figure 1

Planned MW by listed in-service year

Projects listed before 2026 and still planned are past due.

Past dueDue 2026 or later
05001k1.5k Snapshot year 2026 2027 2028 2029 2030 1.3 GW 2031
View as table
YearProjectsMW
202600 MW
20277845.7 MW
20283303.6 MW
202911.2 GW
203000 MW
203131.3 GW
Source. Every planned project lists a date MW

Pipeline by grid and queue year

Hexagon Energy's planned MW leans on PJM Interconnection, ERCOT and New York ISO (NYISO). PJM Interconnection alone holds 72% of it.

Figure 2

Planned MW by grid operator

14 planned projects

PJM Interconnection 2.6 GW 5 projects
ERCOT 1 GW 8 projects
New York ISO (NYISO) 2 MW 1 project
View as table
GridPlanned projectsPlanned MW
PJM Interconnection52.6 GW
ERCOT81 GW
New York ISO (NYISO)12 MW
Source. Balancing authorities as listed in the queue
Figure 3

When the planned projects entered the queue

Planned MW by queue request year. 2023 was the biggest year.

05001k1.5k 2019 2020 2021 2022 1 GW 2023
View as table
Queue yearProjectsMW
20192438 MW
202021 GW
202100 MW
202200 MW
202381 GW
Source. 2 projects without a queue date are left out MW

Hexagon Energy against the nine largest developers

The nine largest planned pipelines in the database, ranked by planned MW. NextEra Energy leads with 36.8 GW planned. Hexagon Energy ranks 44 of 815 developers with a planned project.

#DeveloperPlanned projectsPlanned MWOperating projectsOperating MWOperating per planned
1 NextEra Energy 191
36.8 GW
75
11.7 GW
0.32
2 Invenergy 135
27.1 GW
28
4.5 GW
0.17
3 Intersect Power 54
25.3 GW
5
1.2 GW
0.05
4 Hecate Energy 41
18.1 GW
8
1 GW
0.06
5 Engie 80
17.6 GW
51
4.3 GW
0.24
6 RWE 78
12.8 GW
20
3.2 GW
0.25
7 Avantus 49
12.5 GW
10
1.7 GW
0.14
8 EDF Renewables 54
11.7 GW
15
1.4 GW
0.12
9 OCI Energy 45
10.6 GW
1
100 MW
0.01
44 Hexagon Energy this page 14
3.6 GW
0
0 MW
0.00

Operating per planned is operating MW divided by planned MW. A low ratio means a pipeline far larger than the fleet already built.

Top 9 by planned MW, plus Hexagon Energy

16 people at Hexagon Energy

Contacts with title, seniority, department, email and LinkedIn, counted here and never named. 6 managers and 1 director are where interconnection and procurement decisions start.

Figure 4

By seniority

16 contacts

C-Suite 3
VP 4
Director 1
Manager 6
Senior 2
View as table
SeniorityContacts
C-Suite3
VP4
Director1
Manager6
Senior2
Source. FieldProspects contacts table, counts only

Sample rows

Illustrative rows, names and details removed.

Members only
Seniority: Director and above 16 contacts
PersonTitleDepartmentSeniorityContact
16 contacts at Hexagon Energy for members

Names, titles, direct emails and LinkedIn profiles, matched to the projects they work on.

Request access

Every Hexagon Energy project

All 14 projects with name, county, grid, MW, queue date, in-service date, interconnection status and construction status. Filter, sort and export to Excel.

Members only
Developer: Hexagon EnergySort: MW, largest first 14 projects
ProjectCountyGridMWQueue dateIn serviceAgreement
14 projects and 3.6 GW behind this preview

Project names never appear next to their developer on public pages. Members see both, plus the 16 contacts.

Request access

Get alerts for Hexagon Energy

We email you when Hexagon Energy adds a project, signs an interconnection agreement, starts construction, slips a date or drops a project. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

See every Hexagon Energy project and the 16 people behind them.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.