Geronimo Power
Geronimo Power has 38 planned power projects totaling 5.7 GW and 12 operating projects totaling 1.3 GW in the FieldProspects database. 75% of the planned capacity has an interconnection agreement and 29% is past its listed in-service date. It also has 2 data center records.
Where Geronimo Power's planned pipeline sits
Planned MW by state. The 6 largest states hold 4.8 GW of the 5.7 GW.
for every MW Geronimo Power operates today. Solar is most of the gap.
View as table
| Technology | Planned projects | Planned MW | Operating projects | Operating MW |
|---|---|---|---|---|
| Solar | 29 | 4.2 GW | 11 | 1.2 GW |
| Battery Storage | 8 | 1.2 GW | 1 | 100 MW |
| Wind | 1 | 200 MW | 0 | 0 MW |
MW by technologyWind has no operating projects
How much of the pipeline is real
An interconnection agreement and a construction start are the two strongest signals that a queue project will be built. A listed date that has already passed is the strongest sign it will not be built on time.
Share of Geronimo Power's planned MWSee the queue slip report
Planned MW by listed in-service year
Projects listed before 2026 and still planned are past due.
View as table
| Year | Projects | MW |
|---|---|---|
| 2020 | 1 | 200 MW |
| 2021 | 0 | 0 MW |
| 2022 | 0 | 0 MW |
| 2023 | 2 | 100 MW |
| 2024 | 4 | 415 MW |
| 2025 | 8 | 917 MW |
| 2026 | 6 | 1.1 GW |
| 2027 | 1 | 250 MW |
| 2028 | 10 | 1.8 GW |
| 2029 | 5 | 658.9 MW |
| 2030 | 1 | 250 MW |
Pipeline by grid and queue year
Geronimo Power's planned MW leans on Midcontinent ISO (MISO), ERCOT and PJM Interconnection. Midcontinent ISO (MISO) alone holds 54% of it.
Planned MW by grid operator
38 planned projects
View as table
| Grid | Planned projects | Planned MW |
|---|---|---|
| Midcontinent ISO (MISO) | 22 | 3.1 GW |
| ERCOT | 10 | 1.7 GW |
| PJM Interconnection | 5 | 743 MW |
| Southwest Power Pool (SPP) | 1 | 150 MW |
When the planned projects entered the queue
Planned MW by queue request year. 2020 was the biggest year.
View as table
| Queue year | Projects | MW |
|---|---|---|
| 2016 | 2 | 167 MW |
| 2017 | 1 | 200 MW |
| 2018 | 3 | 180 MW |
| 2019 | 7 | 825 MW |
| 2020 | 9 | 1.5 GW |
| 2021 | 3 | 402.8 MW |
| 2022 | 5 | 955.3 MW |
| 2023 | 1 | 153.6 MW |
| 2024 | 5 | 857.3 MW |
Changes since the June 4, 2026 snapshot
What moved in Geronimo Power's queue position between June 4, 2026 and October 8, 2026.
Which projects were added, finished, cancelled or shelved
| Change | Project | Technology | State | MW | Grid |
|---|---|---|---|---|---|
Members see each changed project with its name, location and dates, and get an email when Geronimo Power's pipeline moves.
Geronimo Power against the nine largest developers
The nine largest planned pipelines in the database, ranked by planned MW. NextEra Energy leads with 36.8 GW planned. Geronimo Power ranks 29 of 815 developers with a planned project.
| # | Developer | Planned projects | Planned MW | Operating projects | Operating MW | Operating per planned |
|---|---|---|---|---|---|---|
| 1 | NextEra Energy | 191 | 75 | 0.32 | ||
| 2 | Invenergy | 135 | 28 | 0.17 | ||
| 3 | Intersect Power | 54 | 5 | 0.05 | ||
| 4 | Hecate Energy | 41 | 8 | 0.06 | ||
| 5 | Engie | 80 | 51 | 0.24 | ||
| 6 | RWE | 78 | 20 | 0.25 | ||
| 7 | Avantus | 49 | 10 | 0.14 | ||
| 8 | EDF Renewables | 54 | 15 | 0.12 | ||
| 9 | OCI Energy | 45 | 1 | 0.01 | ||
| 29 | Geronimo Power this page | 38 | 12 | 0.23 |
Operating per planned is operating MW divided by planned MW. A low ratio means a pipeline far larger than the fleet already built.
Top 9 by planned MW, plus Geronimo PowerEvery Geronimo Power project
All 50 projects with name, county, grid, MW, queue date, in-service date, interconnection status and construction status. Filter, sort and export to Excel.
| Project | County | Grid | MW | Queue date | In service | Agreement |
|---|---|---|---|---|---|---|
Project names never appear next to their developer on public pages. Members see both.
Get alerts for Geronimo Power
We email you when Geronimo Power adds a project, signs an interconnection agreement, starts construction, slips a date or drops a project. One email per snapshot, only when something changed.
See every Geronimo Power project, with its county, dates and queue status.