FieldProspects

Flatiron Energy

Power developer4 projects on record Data as of

Flatiron Energy has 4 planned power projects totaling 895.6 MW in the FieldProspects database and no operating project on record. 72% of the planned capacity has an interconnection agreement and 0% is past its listed in-service date. The projects sit in 2 states and 1 technology.

895.6MW
planned, 4 projects
0MW
operating, 0 projects
645.6MW
interconnection agreement signed, 72% of planned
0MW
under construction, 0 projects
0MW
past due, 0 projects
2
states
Map

Where Flatiron Energy's planned pipeline sits

Planned MW by state. The 2 largest states hold 895.5 MW of the 895.6 MW.

none planned under 250 MW250 to 1,000 MW1,000 to 2,500 MW2,500 to 5,000 MW5,000 MW or more

Largest states

  1. Massachusetts753.9 MW3 projects, 84% of planned
  2. Connecticut141.6 MW1 project, 16% of planned
Source. ISO and RTO interconnection queues and EIA-860M, via FieldProspects Hover a state for its numbers
Planned against delivered
895.6 MWplanned

and no operating project on record yet. Everything here is pipeline.

PlannedOperating
Battery Storage 895.6 MW
none
View as table
TechnologyPlanned projectsPlanned MWOperating projectsOperating MW
Battery Storage4895.6 MW00 MW

MW by technologyBattery Storage has no operating projects

How much of the pipeline is real

An interconnection agreement and a construction start are the two strongest signals that a queue project will be built. A listed date that has already passed is the strongest sign it will not be built on time.

Interconnection agreement signed645.6 MW, 72%
3 of 4 planned projects (75%)
Under construction0 MW, 0%
0 of 4 planned projects (0%)
Past due0 MW, 0%
0 of 4 planned projects (0%)
0% of Flatiron Energy's planned MW in the seven ISO queues is past due, against 11% for all developers.

Share of Flatiron Energy's planned MWSee the queue slip report

Figure 1

Planned MW by listed in-service year

Projects listed before 2026 and still planned are past due.

Past dueDue 2026 or later
0200400600 Snapshot year 2026 453.9 MW 2027 2028 2029
View as table
YearProjectsMW
202600 MW
20272453.9 MW
20281300 MW
20291141.6 MW
Source. Every planned project lists a date MW

Pipeline by grid and queue year

Flatiron Energy's planned MW sits entirely in ISO New England.

Figure 2

Planned MW by grid operator

4 planned projects

ISO New England 895.6 MW 4 projects
View as table
GridPlanned projectsPlanned MW
ISO New England4895.6 MW
Figure 3

When the planned projects entered the queue

Planned MW by queue request year. 2022 was the biggest year.

0100200300400 2021 345.6 MW 2022
View as table
Queue yearProjectsMW
20211300 MW
20222345.6 MW
Source. 1 project without a queue date is left out MW

Changes since the June 4, 2026 snapshot

What moved in Flatiron Energy's queue position between June 4, 2026 and October 8, 2026.

See every change across all developers
+0
projects added, 0 MW
0
came online
0
cancelled, inactive or dropped
1
slipped a date

Which projects were added, finished, cancelled or shelved

Members only
Developer: Flatiron EnergyChange: any 1 change since June 4, 2026
ChangeProjectTechnologyStateMWGrid
1 changed project behind this preview

Members see each changed project with its name, location and dates, and get an email when Flatiron Energy's pipeline moves.

Request access

Flatiron Energy against the nine largest developers

The nine largest planned pipelines in the database, ranked by planned MW. NextEra Energy leads with 36.8 GW planned. Flatiron Energy ranks 189 of 815 developers with a planned project.

#DeveloperPlanned projectsPlanned MWOperating projectsOperating MWOperating per planned
1 NextEra Energy 191
36.8 GW
75
11.7 GW
0.32
2 Invenergy 135
27.1 GW
28
4.5 GW
0.17
3 Intersect Power 54
25.3 GW
5
1.2 GW
0.05
4 Hecate Energy 41
18.1 GW
8
1 GW
0.06
5 Engie 80
17.6 GW
51
4.3 GW
0.24
6 RWE 78
12.8 GW
20
3.2 GW
0.25
7 Avantus 49
12.5 GW
10
1.7 GW
0.14
8 EDF Renewables 54
11.7 GW
15
1.4 GW
0.12
9 OCI Energy 45
10.6 GW
1
100 MW
0.01
189 Flatiron Energy this page 4
895.6 MW
0
0 MW
0.00

Operating per planned is operating MW divided by planned MW. A low ratio means a pipeline far larger than the fleet already built.

Top 9 by planned MW, plus Flatiron Energy

Every Flatiron Energy project

All 4 projects with name, county, grid, MW, queue date, in-service date, interconnection status and construction status. Filter, sort and export to Excel.

Members only
Developer: Flatiron EnergySort: MW, largest first 4 projects
ProjectCountyGridMWQueue dateIn serviceAgreement
4 projects and 895.6 MW behind this preview

Project names never appear next to their developer on public pages. Members see both.

Request access

Get alerts for Flatiron Energy

We email you when Flatiron Energy adds a project, signs an interconnection agreement, starts construction, slips a date or drops a project. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

See every Flatiron Energy project, with its county, dates and queue status.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.