DTE Energy
DTE Energy has 20 planned power projects totaling 2.7 GW and 6 operating projects totaling 662.2 MW in the FieldProspects database. 100% of the planned capacity has an interconnection agreement and 29% is past its listed in-service date. The projects sit in 1 state and 3 technologies.
Where DTE Energy's planned pipeline sits
Planned MW by state. Everything sits in Michigan.
Largest states
- Michigan2.7 GW20 projects, 100% of planned
for every MW DTE Energy operates today. Solar is most of the gap.
View as table
| Technology | Planned projects | Planned MW | Operating projects | Operating MW |
|---|---|---|---|---|
| Solar | 15 | 1.8 GW | 5 | 648.2 MW |
| Wind | 4 | 637.9 MW | 0 | 0 MW |
| Battery Storage | 1 | 220 MW | 1 | 14 MW |
MW by technologyWind has no operating projects
How much of the pipeline is real
An interconnection agreement and a construction start are the two strongest signals that a queue project will be built. A listed date that has already passed is the strongest sign it will not be built on time.
Share of DTE Energy's planned MWSee the queue slip report
Planned MW by listed in-service year
Projects listed before 2026 and still planned are past due.
View as table
| Year | Projects | MW |
|---|---|---|
| 2018 | 1 | 12.5 MW |
| 2019 | 0 | 0 MW |
| 2020 | 2 | 400.2 MW |
| 2021 | 1 | 225.2 MW |
| 2022 | 0 | 0 MW |
| 2023 | 0 | 0 MW |
| 2024 | 1 | 150 MW |
| 2025 | 0 | 0 MW |
| 2026 | 7 | 780 MW |
| 2027 | 4 | 357 MW |
| 2028 | 4 | 766.4 MW |
Pipeline by grid and queue year
DTE Energy's planned MW sits entirely in Midcontinent ISO (MISO).
Planned MW by grid operator
20 planned projects
View as table
| Grid | Planned projects | Planned MW |
|---|---|---|
| Midcontinent ISO (MISO) | 20 | 2.7 GW |
When the planned projects entered the queue
Planned MW by queue request year. 2016 was the biggest year.
View as table
| Queue year | Projects | MW |
|---|---|---|
| 2016 | 2 | 400.2 MW |
| 2017 | 1 | 12.5 MW |
| 2018 | 0 | 0 MW |
| 2019 | 2 | 375.2 MW |
| 2020 | 0 | 0 MW |
| 2021 | 0 | 0 MW |
| 2022 | 0 | 0 MW |
| 2023 | 3 | 375 MW |
Changes since the June 4, 2026 snapshot
What moved in DTE Energy's queue position between June 4, 2026 and October 8, 2026.
Which projects were added, finished, cancelled or shelved
| Change | Project | Technology | State | MW | Grid |
|---|---|---|---|---|---|
Members see each changed project with its name, location and dates, and get an email when DTE Energy's pipeline moves.
DTE Energy against the nine largest developers
The nine largest planned pipelines in the database, ranked by planned MW. NextEra Energy leads with 36.8 GW planned. DTE Energy ranks 58 of 815 developers with a planned project.
| # | Developer | Planned projects | Planned MW | Operating projects | Operating MW | Operating per planned |
|---|---|---|---|---|---|---|
| 1 | NextEra Energy | 191 | 75 | 0.32 | ||
| 2 | Invenergy | 135 | 28 | 0.17 | ||
| 3 | Intersect Power | 54 | 5 | 0.05 | ||
| 4 | Hecate Energy | 41 | 8 | 0.06 | ||
| 5 | Engie | 80 | 51 | 0.24 | ||
| 6 | RWE | 78 | 20 | 0.25 | ||
| 7 | Avantus | 49 | 10 | 0.14 | ||
| 8 | EDF Renewables | 54 | 15 | 0.12 | ||
| 9 | OCI Energy | 45 | 1 | 0.01 | ||
| 58 | DTE Energy this page | 20 | 6 | 0.25 |
Operating per planned is operating MW divided by planned MW. A low ratio means a pipeline far larger than the fleet already built.
Top 9 by planned MW, plus DTE EnergyEvery DTE Energy project
All 26 projects with name, county, grid, MW, queue date, in-service date, interconnection status and construction status. Filter, sort and export to Excel.
| Project | County | Grid | MW | Queue date | In service | Agreement |
|---|---|---|---|---|---|---|
Project names never appear next to their developer on public pages. Members see both.
Get alerts for DTE Energy
We email you when DTE Energy adds a project, signs an interconnection agreement, starts construction, slips a date or drops a project. One email per snapshot, only when something changed.
See every DTE Energy project, with its county, dates and queue status.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.