FieldProspects

Doral Renewables

Power developer30 projects on record Data as of

Doral Renewables has 27 planned power projects totaling 6.9 GW and 3 operating projects totaling 452.5 MW in the FieldProspects database. 74% of the planned capacity has an interconnection agreement and 1% is past its listed in-service date. 43 contacts at the company are on file.

6.9GW
planned, 27 projects
452.5MW
operating, 3 projects
5.2GW
interconnection agreement signed, 74% of planned
2.1GW
under construction, 9 projects
48MW
past due, 1 project
43
contacts on file
Map

Where Doral Renewables' planned pipeline sits

Planned MW by state. The 6 largest states hold 6.9 GW of the 6.9 GW.

none planned under 250 MW250 to 1,000 MW1,000 to 2,500 MW2,500 to 5,000 MW5,000 MW or more

Largest states

  1. Wisconsin2.4 GW4 projects, 34% of planned
  2. Indiana1.8 GW6 projects, 26% of planned
  3. Texas1.4 GW10 projects, 20% of planned
  4. Kansas770 MW3 projects, 11% of planned
  5. Oklahoma538 MW3 projects, 8% of planned
  6. Ohio48 MW1 project, 1% of planned
Source. ISO and RTO interconnection queues and EIA-860M, via FieldProspects Hover a state for its numbers
Planned against delivered
15.3MW planned

for every MW Doral Renewables operates today. Solar is most of the gap.

PlannedOperating
Solar 5.5 GW
452.5 MW
Battery Storage 1.4 GW
none
View as table
TechnologyPlanned projectsPlanned MWOperating projectsOperating MW
Solar155.5 GW3452.5 MW
Battery Storage121.4 GW00 MW

MW by technologyBattery Storage has no operating projects

How much of the pipeline is real

An interconnection agreement and a construction start are the two strongest signals that a queue project will be built. A listed date that has already passed is the strongest sign it will not be built on time.

Interconnection agreement signed5.2 GW, 74%
20 of 27 planned projects (74%)
Under construction2.1 GW, 30%
9 of 27 planned projects (33%)
Past due48 MW, 1%
1 of 27 planned projects (4%)
1% of Doral Renewables' planned MW in the seven ISO queues is past due, against 11% for all developers.

Share of Doral Renewables' planned MWSee the queue slip report

Figure 1

Planned MW by listed in-service year

Projects listed before 2026 and still planned are past due.

Past dueDue 2026 or later
02k4k6k Snapshot year 2025 1 GW 2026 2027 4.4 GW 2028 2029 2030
View as table
YearProjectsMW
2025148 MW
202641 GW
20273703.4 MW
2028144.4 GW
20293572.8 MW
20302206.3 MW
Source. Every planned project lists a date MW

Pipeline by grid and queue year

Doral Renewables' planned MW leans on Midcontinent ISO (MISO), PJM Interconnection and ERCOT. Midcontinent ISO (MISO) alone holds 34% of it.

Figure 2

Planned MW by grid operator

27 planned projects

Midcontinent ISO (MISO) 2.4 GW 4 projects
PJM Interconnection 1.8 GW 7 projects
ERCOT 1.4 GW 10 projects
Southwest Power Pool (SPP) 1.3 GW 6 projects
View as table
GridPlanned projectsPlanned MW
Midcontinent ISO (MISO)42.4 GW
PJM Interconnection71.8 GW
ERCOT101.4 GW
Southwest Power Pool (SPP)61.3 GW
Source. Balancing authorities as listed in the queue
Figure 3

When the planned projects entered the queue

Planned MW by queue request year. 2022 was the biggest year.

01k2k3k 2016 2017 2018 2019 2020 2021 2.5 GW 2022 2023 2024
View as table
Queue yearProjectsMW
2016148 MW
201700 MW
201800 MW
201900 MW
20203900 MW
202100 MW
202292.5 GW
20236986.7 MW
20242206.3 MW
Source. 6 projects without a queue date are left out MW

Changes since the June 4, 2026 snapshot

What moved in Doral Renewables' queue position between June 4, 2026 and October 8, 2026.

See every change across all developers
+0
projects added, 0 MW
0
came online
1
cancelled, inactive or dropped
7
slipped a date

Which projects were added, finished, cancelled or shelved

Members only
Developer: Doral RenewablesChange: any 8 changes since June 4, 2026
ChangeProjectTechnologyStateMWGrid
8 changed projects behind this preview

Members see each changed project with its name, location and dates, and get an email when Doral Renewables' pipeline moves.

Request access

Doral Renewables against the nine largest developers

The nine largest planned pipelines in the database, ranked by planned MW. NextEra Energy leads with 36.8 GW planned. Doral Renewables ranks 21 of 815 developers with a planned project.

#DeveloperPlanned projectsPlanned MWOperating projectsOperating MWOperating per planned
1 NextEra Energy 191
36.8 GW
75
11.7 GW
0.32
2 Invenergy 135
27.1 GW
28
4.5 GW
0.17
3 Intersect Power 54
25.3 GW
5
1.2 GW
0.05
4 Hecate Energy 41
18.1 GW
8
1 GW
0.06
5 Engie 80
17.6 GW
51
4.3 GW
0.24
6 RWE 78
12.8 GW
20
3.2 GW
0.25
7 Avantus 49
12.5 GW
10
1.7 GW
0.14
8 EDF Renewables 54
11.7 GW
15
1.4 GW
0.12
9 OCI Energy 45
10.6 GW
1
100 MW
0.01
21 Doral Renewables this page 27
6.9 GW
3
452.5 MW
0.07

Operating per planned is operating MW divided by planned MW. A low ratio means a pipeline far larger than the fleet already built.

Top 9 by planned MW, plus Doral Renewables

43 people at Doral Renewables

Contacts with title, seniority, department, email and LinkedIn, counted here and never named. 15 managers and 12 directors are where interconnection and procurement decisions start.

Figure 4

By seniority

43 contacts

C-Suite 3
VP 11
Director 12
Manager 15
Senior 2
View as table
SeniorityContacts
C-Suite3
VP11
Director12
Manager15
Senior2
Source. FieldProspects contacts table, counts only

Sample rows

Illustrative rows, names and details removed.

Members only
Seniority: Director and above 43 contacts
PersonTitleDepartmentSeniorityContact
43 contacts at Doral Renewables for members

Names, titles, direct emails and LinkedIn profiles, matched to the projects they work on.

Request access

Every Doral Renewables project

All 30 projects with name, county, grid, MW, queue date, in-service date, interconnection status and construction status. Filter, sort and export to Excel.

Members only
Developer: Doral RenewablesSort: MW, largest first 30 projects
ProjectCountyGridMWQueue dateIn serviceAgreement
30 projects and 7.4 GW behind this preview

Project names never appear next to their developer on public pages. Members see both, plus the 43 contacts.

Request access

Get alerts for Doral Renewables

We email you when Doral Renewables adds a project, signs an interconnection agreement, starts construction, slips a date or drops a project. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

See every Doral Renewables project and the 43 people behind them.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.