FieldProspects

Con Edison Development

Power developer23 projects on record Data as of

Con Edison Development has 11 planned power projects totaling 1.4 GW and 12 operating projects totaling 1 GW in the FieldProspects database. 16% of the planned capacity has an interconnection agreement and 0% is past its listed in-service date. The projects sit in 7 states and 4 technologies.

1.4GW
planned, 11 projects
1GW
operating, 12 projects
225MW
interconnection agreement signed, 16% of planned
0MW
under construction, 0 projects
0MW
past due, 0 projects
7
states
Map

Where Con Edison Development's planned pipeline sits

Planned MW by state. The 5 largest states hold 1.4 GW of the 1.4 GW.

none planned under 250 MW250 to 1,000 MW1,000 to 2,500 MW2,500 to 5,000 MW5,000 MW or more

Largest states

  1. Texas1.1 GW5 projects, 74% of planned
  2. California225 MW2 projects, 16% of planned
  3. Nebraska75 MW1 project, 5% of planned
  4. Virginia70 MW1 project, 5% of planned
  5. New York0 MW2 projects, 0% of planned
Source. ISO and RTO interconnection queues and EIA-860M, via FieldProspects Hover a state for its numbers
Planned against delivered
1.4MW planned

for every MW Con Edison Development operates today. Battery Storage is most of the gap.

PlannedOperating
Solar 820 MW
694.5 MW
Battery Storage 525 MW
335.1 MW
Wind 75 MW
none
Transmission none
none
View as table
TechnologyPlanned projectsPlanned MWOperating projectsOperating MW
Solar4820 MW5694.5 MW
Battery Storage4525 MW7335.1 MW
Wind175 MW00 MW
Transmission20 MW00 MW

MW by technologyWind and Transmission have no operating projects

How much of the pipeline is real

An interconnection agreement and a construction start are the two strongest signals that a queue project will be built. A listed date that has already passed is the strongest sign it will not be built on time.

Interconnection agreement signed225 MW, 16%
2 of 11 planned projects (18%)
Under construction0 MW, 0%
0 of 11 planned projects (0%)
Past due0 MW, 0%
0 of 11 planned projects (0%)
0% of Con Edison Development's planned MW in the seven ISO queues is past due, against 11% for all developers.

Share of Con Edison Development's planned MWSee the queue slip report

Figure 1

Planned MW by listed in-service year

Projects listed before 2026 and still planned are past due.

Past dueDue 2026 or later
0200400600800 Snapshot year 225 MW 2026 675 MW 2027 2028
View as table
YearProjectsMW
20262225 MW
20274675 MW
20283520 MW
Source. 2 projects with no listed date are left out MW

Pipeline by grid and queue year

Con Edison Development's planned MW leans on ERCOT, California ISO (CAISO) and Southwest Power Pool (SPP). ERCOT alone holds 74% of it.

Figure 2

Planned MW by grid operator

11 planned projects

ERCOT 1.1 GW 5 projects
California ISO (CAISO) 225 MW 2 projects
Southwest Power Pool (SPP) 75 MW 1 project
PJM Interconnection 70 MW 1 project
New York ISO (NYISO) 0 MW 2 projects
View as table
GridPlanned projectsPlanned MW
ERCOT51.1 GW
California ISO (CAISO)2225 MW
Southwest Power Pool (SPP)175 MW
PJM Interconnection170 MW
New York ISO (NYISO)20 MW
Source. Balancing authorities as listed in the queue
Figure 3

When the planned projects entered the queue

Planned MW by queue request year. 2022 was the biggest year.

0200400600 2021 600 MW 2022 2023 2024
View as table
Queue yearProjectsMW
20212150 MW
20223600 MW
202300 MW
202410 MW
Source. 5 projects without a queue date are left out MW

Changes since the June 4, 2026 snapshot

What moved in Con Edison Development's queue position between June 4, 2026 and October 8, 2026.

See every change across all developers
+0
projects added, 0 MW
0
came online
0
cancelled, inactive or dropped
4
slipped a date

Which projects were added, finished, cancelled or shelved

Members only
Developer: Con Edison DevelopmentChange: any 4 changes since June 4, 2026
ChangeProjectTechnologyStateMWGrid
4 changed projects behind this preview

Members see each changed project with its name, location and dates, and get an email when Con Edison Development's pipeline moves.

Request access

Con Edison Development against the nine largest developers

The nine largest planned pipelines in the database, ranked by planned MW. NextEra Energy leads with 36.8 GW planned. Con Edison Development ranks 109 of 815 developers with a planned project.

#DeveloperPlanned projectsPlanned MWOperating projectsOperating MWOperating per planned
1 NextEra Energy 191
36.8 GW
75
11.7 GW
0.32
2 Invenergy 135
27.1 GW
28
4.5 GW
0.17
3 Intersect Power 54
25.3 GW
5
1.2 GW
0.05
4 Hecate Energy 41
18.1 GW
8
1 GW
0.06
5 Engie 80
17.6 GW
51
4.3 GW
0.24
6 RWE 78
12.8 GW
20
3.2 GW
0.25
7 Avantus 49
12.5 GW
10
1.7 GW
0.14
8 EDF Renewables 54
11.7 GW
15
1.4 GW
0.12
9 OCI Energy 45
10.6 GW
1
100 MW
0.01
109 Con Edison Development this page 11
1.4 GW
12
1 GW
0.73

Operating per planned is operating MW divided by planned MW. A low ratio means a pipeline far larger than the fleet already built.

Top 9 by planned MW, plus Con Edison Development

Every Con Edison Development project

All 23 projects with name, county, grid, MW, queue date, in-service date, interconnection status and construction status. Filter, sort and export to Excel.

Members only
Developer: Con Edison DevelopmentSort: MW, largest first 23 projects
ProjectCountyGridMWQueue dateIn serviceAgreement
23 projects and 2.4 GW behind this preview

Project names never appear next to their developer on public pages. Members see both.

Request access

Get alerts for Con Edison Development

We email you when Con Edison Development adds a project, signs an interconnection agreement, starts construction, slips a date or drops a project. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

See every Con Edison Development project, with its county, dates and queue status.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.