Avangrid Renewables

Power developer30 projects on record Data as of

Avangrid Renewables has 22 planned power projects totaling 4.1 GW and 8 operating projects totaling 1.7 GW in the FieldProspects database. 88% of the planned capacity has an interconnection agreement and 2% is past its listed in-service date. The projects sit in 11 states and 3 technologies.

4.1GW
planned, 22 projects
1.7GW
operating, 8 projects
3.6GW
interconnection agreement signed, 88% of planned
1.3GW
under construction, 5 projects
100MW
past due, 1 project
11
states
Map

Where Avangrid Renewables' planned pipeline sits

Planned MW by state. The 6 largest states hold 3.8 GW of the 4.1 GW.

none planned under 250 MW250 to 1,000 MW1,000 to 2,500 MW2,500 to 5,000 MW5,000 MW or more

Largest states

  1. Massachusetts1.6 GW3 projects, 39% of planned
  2. Ohio962 MW4 projects, 24% of planned
  3. Illinois750 MW5 projects, 18% of planned
  4. California182.6 MW3 projects, 4% of planned
  5. Kentucky160 MW2 projects, 4% of planned
  6. Oregon144 MW2 projects, 4% of planned

3 more states with less.

Source. ISO and RTO interconnection queues and EIA-860M, via FieldProspects Hover a state for its numbers
Planned against delivered
2.4MW planned

for every MW Avangrid Renewables operates today. Solar is most of the gap.

PlannedOperating
Solar 2.1 GW
764.5 MW
Wind 2 GW
947.5 MW
Battery Storage 11 MW
none
View as table
TechnologyPlanned projectsPlanned MWOperating projectsOperating MW
Solar152.1 GW6764.5 MW
Wind62 GW2947.5 MW
Battery Storage111 MW00 MW

MW by technologyBattery Storage has no operating projects

How much of the pipeline is real

An interconnection agreement and a construction start are the two strongest signals that a queue project will be built. A listed date that has already passed is the strongest sign it will not be built on time.

Interconnection agreement signed3.6 GW, 88%
17 of 22 planned projects (77%)
Under construction1.3 GW, 32%
5 of 22 planned projects (23%)
Past due100 MW, 2%
1 of 22 planned projects (5%)
3% of Avangrid Renewables' planned MW in the seven ISO queues is past due, against 11% for all developers.

Share of Avangrid Renewables' planned MWSee the queue slip report

Figure 1

Planned MW by listed in-service year

Projects listed before 2026 and still planned are past due.

Past dueDue 2026 or later
05001k1.5k Snapshot year 2023 2024 2025 1.1 GW 2026 2027 2028 1.2 GW 2029 2030
View as table
YearProjectsMW
20231100 MW
202400 MW
202500 MW
202631.1 GW
202791.2 GW
20283283 MW
202951.2 GW
20301127.6 MW
Source. Every planned project lists a date MW

Pipeline by grid and queue year

Avangrid Renewables' planned MW leans on PJM Interconnection, ISO New England and California ISO (CAISO). PJM Interconnection alone holds 48% of it.

Figure 2

Planned MW by grid operator

22 planned projects

PJM Interconnection 2 GW 12 projects
ISO New England 1.6 GW 3 projects
California ISO (CAISO) 182.6 MW 3 projects
Bonneville Power Administration 144 MW 2 projects
Midcontinent ISO (MISO) 100 MW 1 project
New York ISO (NYISO) 90.5 MW 1 project
View as table
GridPlanned projectsPlanned MW
PJM Interconnection122 GW
ISO New England31.6 GW
California ISO (CAISO)3182.6 MW
Bonneville Power Administration2144 MW
Midcontinent ISO (MISO)1100 MW
New York ISO (NYISO)190.5 MW
Source. Balancing authorities as listed in the queue
Figure 3

When the planned projects entered the queue

Planned MW by queue request year. 2017 was the biggest year.

05001k1.5k 2008 2009 2010 2011 2012 2013 2014 2015 2016 1.2 GW 2017 2018 2019 2020 2021
View as table
Queue yearProjectsMW
200800 MW
200900 MW
201000 MW
201100 MW
201200 MW
201300 MW
201400 MW
201500 MW
20161800 MW
201741.2 GW
20183646 MW
20192250 MW
20203380 MW
202110 MW
Source. 7 projects without a queue date are left out MW

Changes since the June 4, 2026 snapshot

What moved in Avangrid Renewables' queue position between June 4, 2026 and October 8, 2026.

See every change across all developers
+3
projects added, 916 MW
1
came online
0
cancelled, inactive or dropped
1
slipped a date

Which projects were added, finished, cancelled or shelved

Members only
Developer: Avangrid RenewablesChange: any 5 changes since June 4, 2026
ChangeProjectTechnologyStateMWGrid
5 changed projects behind this preview

Members see each changed project with its name, location and dates, and get an email when Avangrid Renewables' pipeline moves.

Request access

Avangrid Renewables against the nine largest developers

The nine largest planned pipelines in the database, ranked by planned MW. NextEra Energy leads with 36.8 GW planned. Avangrid Renewables ranks 40 of 815 developers with a planned project.

#DeveloperPlanned projectsPlanned MWOperating projectsOperating MWOperating per planned
1 NextEra Energy 191
36.8 GW
75
11.7 GW
0.32
2 Invenergy 135
27.1 GW
28
4.5 GW
0.17
3 Intersect Power 54
25.3 GW
5
1.2 GW
0.05
4 Hecate Energy 41
18.1 GW
8
1 GW
0.06
5 Engie 80
17.6 GW
51
4.3 GW
0.24
6 RWE 78
12.8 GW
20
3.2 GW
0.25
7 Avantus 49
12.5 GW
10
1.7 GW
0.14
8 EDF Renewables 54
11.7 GW
15
1.4 GW
0.12
9 OCI Energy 45
10.6 GW
1
100 MW
0.01
40 Avangrid Renewables this page 22
4.1 GW
8
1.7 GW
0.42

Operating per planned is operating MW divided by planned MW. A low ratio means a pipeline far larger than the fleet already built.

Top 9 by planned MW, plus Avangrid Renewables

Every Avangrid Renewables project

All 30 projects with name, county, grid, MW, queue date, in-service date, interconnection status and construction status. Filter, sort and export to Excel.

Members only
Developer: Avangrid RenewablesSort: MW, largest first 30 projects
ProjectCountyGridMWQueue dateIn serviceAgreement
30 projects and 5.8 GW behind this preview

Project names never appear next to their developer on public pages. Members see both.

Request access

Get alerts for Avangrid Renewables

We email you when Avangrid Renewables adds a project, signs an interconnection agreement, starts construction, slips a date or drops a project. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

See every Avangrid Renewables project, with its county, dates and queue status.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.