Ameren Missouri

Power developer8 projects on record Data as of

Ameren Missouri has 4 planned power projects totaling 709.9 MW and 4 operating projects totaling 400 MW in the FieldProspects database. 100% of the planned capacity has an interconnection agreement and 58% is past its listed in-service date. The projects sit in 2 states and 2 technologies.

709.9MW
planned, 4 projects
400MW
operating, 4 projects
709.9MW
interconnection agreement signed, 100% of planned
149.9MW
under construction, 1 project
409.9MW
past due, 3 projects
2
states
Map

Where Ameren Missouri's planned pipeline sits

Planned MW by state. The 2 largest states hold 709.9 MW of the 709.9 MW.

none planned under 250 MW250 to 1,000 MW1,000 to 2,500 MW2,500 to 5,000 MW5,000 MW or more

Largest states

  1. Missouri560 MW3 projects, 79% of planned
  2. Illinois149.9 MW1 project, 21% of planned
Source. ISO and RTO interconnection queues and EIA-860M, via FieldProspects Hover a state for its numbers
Planned against delivered
1.8MW planned

for every MW Ameren Missouri operates today. Solar is most of the gap.

PlannedOperating
Solar 649.9 MW
400 MW
Hydro 60 MW
none
View as table
TechnologyPlanned projectsPlanned MWOperating projectsOperating MW
Solar3649.9 MW4400 MW
Hydro160 MW00 MW

MW by technologyHydro has no operating projects

How much of the pipeline is real

An interconnection agreement and a construction start are the two strongest signals that a queue project will be built. A listed date that has already passed is the strongest sign it will not be built on time.

Interconnection agreement signed709.9 MW, 100%
4 of 4 planned projects (100%)
Under construction149.9 MW, 21%
1 of 4 planned projects (25%)
Past due409.9 MW, 58%
3 of 4 planned projects (75%)
58% of Ameren Missouri's planned MW in the seven ISO queues is past due, against 11% for all developers.

Share of Ameren Missouri's planned MWSee the queue slip report

Figure 1

Planned MW by listed in-service year

Projects listed before 2026 and still planned are past due.

Past dueDue 2026 or later
0100200300 Snapshot year 2022 2023 2024 2025 2026 300 MW 2027
View as table
YearProjectsMW
20221149.9 MW
202300 MW
20242260 MW
202500 MW
202600 MW
20271300 MW
Source. Every planned project lists a date MW

Pipeline by grid and queue year

Ameren Missouri's planned MW sits entirely in Midcontinent ISO (MISO).

Figure 2

Planned MW by grid operator

4 planned projects

Midcontinent ISO (MISO) 709.9 MW 4 projects
View as table
GridPlanned projectsPlanned MW
Midcontinent ISO (MISO)4709.9 MW
Figure 3

When the planned projects entered the queue

Planned MW by queue request year. 2020 was the biggest year.

0100200300 2017 2018 2019 300 MW 2020
View as table
Queue yearProjectsMW
20171149.9 MW
20181200 MW
2019160 MW
20201300 MW
Source. Every planned project has a queue date MW

Changes since the June 4, 2026 snapshot

What moved in Ameren Missouri's queue position between June 4, 2026 and October 8, 2026.

See every change across all developers
+0
projects added, 0 MW
0
came online
0
cancelled, inactive or dropped
1
slipped a date

Which projects were added, finished, cancelled or shelved

Members only
Developer: Ameren MissouriChange: any 1 change since June 4, 2026
ChangeProjectTechnologyStateMWGrid
1 changed project behind this preview

Members see each changed project with its name, location and dates, and get an email when Ameren Missouri's pipeline moves.

Request access

Ameren Missouri against the nine largest developers

The nine largest planned pipelines in the database, ranked by planned MW. NextEra Energy leads with 36.8 GW planned. Ameren Missouri ranks 226 of 815 developers with a planned project.

#DeveloperPlanned projectsPlanned MWOperating projectsOperating MWOperating per planned
1 NextEra Energy 191
36.8 GW
75
11.7 GW
0.32
2 Invenergy 135
27.1 GW
28
4.5 GW
0.17
3 Intersect Power 54
25.3 GW
5
1.2 GW
0.05
4 Hecate Energy 41
18.1 GW
8
1 GW
0.06
5 Engie 80
17.6 GW
51
4.3 GW
0.24
6 RWE 78
12.8 GW
20
3.2 GW
0.25
7 Avantus 49
12.5 GW
10
1.7 GW
0.14
8 EDF Renewables 54
11.7 GW
15
1.4 GW
0.12
9 OCI Energy 45
10.6 GW
1
100 MW
0.01
226 Ameren Missouri this page 4
709.9 MW
4
400 MW
0.56

Operating per planned is operating MW divided by planned MW. A low ratio means a pipeline far larger than the fleet already built.

Top 9 by planned MW, plus Ameren Missouri

Every Ameren Missouri project

All 8 projects with name, county, grid, MW, queue date, in-service date, interconnection status and construction status. Filter, sort and export to Excel.

Members only
Developer: Ameren MissouriSort: MW, largest first 8 projects
ProjectCountyGridMWQueue dateIn serviceAgreement
8 projects and 1.1 GW behind this preview

Project names never appear next to their developer on public pages. Members see both.

Request access

Get alerts for Ameren Missouri

We email you when Ameren Missouri adds a project, signs an interconnection agreement, starts construction, slips a date or drops a project. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

See every Ameren Missouri project, with its county, dates and queue status.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.