Power developer1 project on record Data as of

NorthStar Clean Energy has 1 planned power project totaling 120 MW in the FieldProspects database and no operating project on record. 100% of the planned capacity has an interconnection agreement and 0% is past its listed in-service date. 37 contacts at the company are on file.

120MW
planned, 1 project
0MW
operating, 0 projects
120MW
interconnection agreement signed, 100% of planned
120MW
under construction, 1 project
0MW
past due, 0 projects
37
contacts on file
Map

Where NorthStar Clean Energy's planned pipeline sits

Planned MW by state. Everything sits in Michigan.

none planned under 250 MW250 to 1,000 MW1,000 to 2,500 MW2,500 to 5,000 MW5,000 MW or more

Largest states

  1. Michigan120 MW1 project, 100% of planned
Source. ISO and RTO interconnection queues and EIA-860M, via FieldProspects Hover a state for its numbers
Planned against delivered
120 MWplanned

and no operating project on record yet. Everything here is pipeline.

PlannedOperating
Solar 120 MW
none
View as table
TechnologyPlanned projectsPlanned MWOperating projectsOperating MW
Solar1120 MW00 MW

MW by technologySolar has no operating projects

How much of the pipeline is real

An interconnection agreement and a construction start are the two strongest signals that a queue project will be built. A listed date that has already passed is the strongest sign it will not be built on time.

Interconnection agreement signed120 MW, 100%
1 of 1 planned project (100%)
Under construction120 MW, 100%
1 of 1 planned project (100%)
Past due0 MW, 0%
0 of 1 planned project (0%)
0% of NorthStar Clean Energy's planned MW in the seven ISO queues is past due, against 11% for all developers.

Share of NorthStar Clean Energy's planned MWSee the queue slip report

Figure 1

Planned MW by listed in-service year

Projects listed before 2026 and still planned are past due.

Past dueDue 2026 or later
050100150 Snapshot year 120 MW 2026
View as table
YearProjectsMW
20261120 MW
Source. Every planned project lists a date MW

Pipeline by grid and queue year

NorthStar Clean Energy's planned MW sits entirely in Midcontinent ISO (MISO).

Figure 2

Planned MW by grid operator

1 planned project

Midcontinent ISO (MISO) 120 MW 1 project
View as table
GridPlanned projectsPlanned MW
Midcontinent ISO (MISO)1120 MW

NorthStar Clean Energy against the nine largest developers

The nine largest planned pipelines in the database, ranked by planned MW. NextEra Energy leads with 36.8 GW planned. NorthStar Clean Energy ranks 605 of 815 developers with a planned project.

#DeveloperPlanned projectsPlanned MWOperating projectsOperating MWOperating per planned
1 NextEra Energy 191
36.8 GW
75
11.7 GW
0.32
2 Invenergy 135
27.1 GW
28
4.5 GW
0.17
3 Intersect Power 54
25.3 GW
5
1.2 GW
0.05
4 Hecate Energy 41
18.1 GW
8
1 GW
0.06
5 Engie 80
17.6 GW
51
4.3 GW
0.24
6 RWE 78
12.8 GW
20
3.2 GW
0.25
7 Avantus 49
12.5 GW
10
1.7 GW
0.14
8 EDF Renewables 54
11.7 GW
15
1.4 GW
0.12
9 OCI Energy 45
10.6 GW
1
100 MW
0.01
605 NorthStar Clean Energy this page 1
120 MW
0
0 MW
0.00

Operating per planned is operating MW divided by planned MW. A low ratio means a pipeline far larger than the fleet already built.

Top 9 by planned MW, plus NorthStar Clean Energy

37 people at NorthStar Clean Energy

Contacts with title, seniority, department, email and LinkedIn, counted here and never named. 12 managers and 9 directors are where interconnection and procurement decisions start.

Figure 3

By seniority

37 contacts

C-Suite 4
Partner 6
VP 1
Director 9
Manager 12
Senior 5
View as table
SeniorityContacts
C-Suite4
Partner6
VP1
Director9
Manager12
Senior5
Source. FieldProspects contacts table, counts only

Sample rows

Illustrative rows, names and details removed.

Members only
Seniority: Director and above 37 contacts
PersonTitleDepartmentSeniorityContact
37 contacts at NorthStar Clean Energy for members

Names, titles, direct emails and LinkedIn profiles, matched to the projects they work on.

Request access

Every NorthStar Clean Energy project

The one project with name, county, grid, MW, queue date, in-service date, interconnection status and construction status. Filter, sort and export to Excel.

Members only
Developer: NorthStar Clean EnergySort: MW, largest first 1 project
ProjectCountyGridMWQueue dateIn serviceAgreement
1 project and 120 MW behind this preview

Project names never appear next to their developer on public pages. Members see both, plus the 37 contacts.

Request access

Get alerts for NorthStar Clean Energy

We email you when NorthStar Clean Energy adds a project, signs an interconnection agreement, starts construction, slips a date or drops a project. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

See every NorthStar Clean Energy project and the 37 people behind them.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.