Gore Street Energy Storage Fund
Gore Street Energy Storage Fund has 2 operating power projects totaling 275 MW in the FieldProspects database and no planned project in any queue. The projects sit in 2 states and 1 technology. Battery Storage is its largest technology by capacity.
Where Gore Street Energy Storage Fund's operating fleet sits
Operating MW by state. The 2 largest states hold 275 MW of the 275 MW.
Largest states
- California200 MW1 project, 73% of operating
- Texas75 MW1 project, 27% of operating
and nothing planned in any queue. All of it is already built.
View as table
| Technology | Planned projects | Planned MW | Operating projects | Operating MW |
|---|---|---|---|---|
| Battery Storage | 0 | 0 MW | 2 | 275 MW |
MW by technologyPlanned and operating MW
Gore Street Energy Storage Fund against the nine largest developers
The nine largest planned pipelines in the database, ranked by planned MW. Gore Street Energy Storage Fund has no planned project on record, so it sits below every developer in this table.
| # | Developer | Planned projects | Planned MW | Operating projects | Operating MW | Operating per planned |
|---|---|---|---|---|---|---|
| 1 | NextEra Energy | 191 | 75 | 0.32 | ||
| 2 | Invenergy | 135 | 28 | 0.17 | ||
| 3 | Intersect Power | 54 | 5 | 0.05 | ||
| 4 | Hecate Energy | 41 | 8 | 0.06 | ||
| 5 | Engie | 80 | 51 | 0.24 | ||
| 6 | RWE | 78 | 20 | 0.25 | ||
| 7 | Avantus | 49 | 10 | 0.14 | ||
| 8 | EDF Renewables | 54 | 15 | 0.12 | ||
| 9 | OCI Energy | 45 | 1 | 0.01 | ||
| Gore Street Energy Storage Fund this page | 0 | 2 | no planned MW |
Operating per planned is operating MW divided by planned MW. A low ratio means a pipeline far larger than the fleet already built.
Top 9 by planned MW, plus Gore Street Energy Storage FundEvery Gore Street Energy Storage Fund project
All 2 projects with name, county, grid, MW, queue date, in-service date, interconnection status and construction status. Filter, sort and export to Excel.
| Project | County | Grid | MW | Queue date | In service | Agreement |
|---|---|---|---|---|---|---|
Project names never appear next to their developer on public pages. Members see both.
Get alerts for Gore Street Energy Storage Fund
We email you when Gore Street Energy Storage Fund adds a project, signs an interconnection agreement, starts construction, slips a date or drops a project. One email per snapshot, only when something changed.
See every Gore Street Energy Storage Fund project, with its county, dates and queue status.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.