ERCOT interconnection queue

ERCOT interconnection queue: planned projects by technology and year

The ERCOT interconnection queue in the FieldProspects database lists 2,359 planned power projects totalling 532.2 GW, alongside 2,290 operating projects. Solar is the largest planned technology at 190 GW, and battery storage follows at 186 GW. Every planned project is in Texas.

Data as of

What is the ERCOT interconnection queue?

The ERCOT interconnection queue is the list of power plants and battery projects that have asked the Electric Reliability Council of Texas for permission to connect to its grid. Each request is studied before it may connect, so the list shows what developers intend to build well before construction starts.

ERCOT planned and operating projects

The planned ERCOT pipeline is 2.9 times the capacity of the operating fleet: 532.2 GW across 2,359 projects, against 182 GW across 2,290. Of the planned entries, 1,835 come from the ERCOT generator interconnection queue and 524 are planned units from federal generator filings.

Battery storage has the most entries, 1,047, while solar has the most capacity. The gap is size: among entries that state a capacity, the average planned solar entry is 239.8 MW and the average planned battery entry is 189.5 MW. Natural gas adds 320 entries and 95.4 GW, and wind 179 entries and 53.3 GW.

Every planned ERCOT project in the database is in Texas, so the grid and the state describe the same pipeline.

ERCOT at a glance
Planned projects 2,359
Planned capacity 532.2 GW
Operating projects 2,290
Operating capacity 182 GW
Planned projects with a developer attributed 70.7% (1,668 of 2,359)
Operating projects with a developer attributed 12% (275 of 2,290)
ERCOT projects by technology
TechnologyPlanned projectsPlanned capacityOperating projectsOperating capacity
Solar 795 190 GW 244 32.7 GW
Battery Storage 1,047 186 GW 261 18.2 GW
Natural Gas 320 95.4 GW 1,175 69.2 GW
Wind 179 53.3 GW 210 40.5 GW
Nuclear 4 4.5 GW 4 5.1 GW
Other 7 2.8 GW 5 125.1 MW
Oil 4 161.8 MW 305 822.1 MW
Hydrogen 1 79.6 MW None None
Waste Heat 2 28.6 MW 8 158.2 MW
Coal None None 21 14.3 GW
Hydro None None 37 567.5 MW
Biomass None None 1 114 MW
Petroleum Coke None None 3 61.9 MW
Landfill Gas None None 16 23 MW
All technologies 2,359 532.2 GW 2,290 182 GW

When ERCOT projects are expected in service

Expected in-service years run from 2026 to 2033. 2028 is the peak, with 713 projects and 163.4 GW, and 2027 to 2029 together hold 1,751 projects and 74.7% of planned capacity. Only 29 entries carry a year that has already passed, and none lack a date.

These are the expected in-service dates given in the sources. They record an intention, not a commitment.

Planned ERCOT projects by expected in-service year
Expected in-service yearProjectsCapacityShare of capacity
Before 2026, still listed as planned 29 3.1 GW 0.6%
2026 289 46.7 GW 8.8%
2027 554 109.5 GW 20.6%
2028 713 163.4 GW 30.7%
2029 484 124.7 GW 23.4%
2030 256 61.9 GW 11.6%
2031 16 8.7 GW 1.6%
2032 15 13.1 GW 2.5%
2033 3 1.1 GW 0.2%
All planned projects 2,359 532.2 GW 100%

Five of the largest planned ERCOT entries

The five large planned ERCOT entries shown here run from 1.5 GW to 2 GW, against an average of 233.1 MW across the 2,283 planned entries that state a capacity. Names are shown as the source lists them. An entry can be one unit or one phase of a larger plant, so each figure is that entry alone.

Large planned ERCOT entries by capacity
Entry nameCapacity
BM Great Rock Energy Center 2 GW
Prairie Ridge (Gas - CC) 1.7 GW
Aegle Power 1.5 GW
Big Canyon Wind 1.5 GW
Caldwell County Energy Center 1.5 GW

What the database adds for ERCOT

On this page a planned project is a name and a number. In the database each of the 2,359 planned ERCOT rows also carries its county and status, the developer where one is attributed, and the contacts at that developer. A developer is attributed on 70.7% of planned ERCOT projects (1,668 of 2,359), the highest share among the four grids with a page here, and on 12% of operating ones.

Filter the ERCOT rows by technology, capacity band, county, year or developer, and export the filtered list as CSV or Excel.

Source. ERCOT generator interconnection queue and U.S. Energy Information Administration Form EIA-860M, compiled by FieldProspects.