CAISO interconnection queue: where battery storage outweighs solar

The CAISO interconnection queue in the FieldProspects database lists 780 planned power projects totalling 186.2 GW, next to 100.3 GW already operating on that grid. Battery storage, not solar, leads the pipeline with 415 entries and 100.6 GW, ahead of solar at 72.2 GW.

Data as of

What is the CAISO interconnection queue?

The CAISO interconnection queue is the set of generation and storage projects that have applied to connect to the grid run by the California Independent System Operator. Developers join the list to have their connection studied, so it shows which projects are seeking a connection to the CAISO grid.

CAISO planned and operating projects

The planned CAISO pipeline is 1.9 times the capacity of the operating fleet. Battery storage accounts for 54% of it, and the planned batteries are 5.9 times the 17.1 GW already in operation. Solar has the larger base today, 25.8 GW operating, and 72.2 GW planned.

Natural gas is the clearest contrast: 32.4 GW operates on the CAISO grid, yet only 9 gas entries totalling 1.1 GW are planned. Wind adds 35 entries and 9.9 GW. Of the 780 planned entries, 562 come from the CAISO interconnection queue and 218 are planned units from federal generator filings.

CAISO at a glance
Planned projects 780
Planned capacity 186.2 GW
Operating projects 2,858
Operating capacity 100.3 GW
Planned projects with a developer attributed 42.2% (329 of 780)
Operating projects with a developer attributed 9.9% (283 of 2,858)
CAISO projects by technology
TechnologyPlanned projectsPlanned capacityOperating projectsOperating capacity
Battery Storage 415 100.6 GW 310 17.1 GW
Solar 298 72.2 GW 1,068 25.8 GW
Wind 35 9.9 GW 131 10 GW
Other 5 1.6 GW 5 21 MW
Natural Gas 9 1.1 GW 629 32.4 GW
Hydro 8 682 MW 346 8.8 GW
Geothermal 2 62.4 MW 42 2.2 GW
Landfill Gas 5 9.4 MW 102 274.1 MW
Biomass 3 7.6 MW 95 732.5 MW
Nuclear None None 2 2.3 GW
Oil None None 121 439.3 MW
Coal None None 3 62.5 MW
Waste Heat None None 4 49.7 MW
All technologies 780 186.2 GW 2,858 100.3 GW

CAISO projects by state

California holds 669 of the 780 planned entries and 77% of the capacity. The other 111 entries sit in Nevada, Arizona and Wyoming, which the database assigns to the CAISO grid: Nevada adds 20.4 GW, Arizona 18.8 GW and Wyoming 3.6 GW.

Planned CAISO projects by state
StateProjectsCapacityShare of capacity
California 669 143.4 GW 77%
Nevada 61 20.4 GW 11%
Arizona 46 18.8 GW 10.1%
Wyoming 4 3.6 GW 1.9%

When CAISO projects are expected in service

Every planned CAISO entry carries an expected year, and they run out to 2035. Only 41 entries, 5.3% of the list, carry a year that has already passed.

2027 has the most entries, 166, but 2028 holds the most capacity, 39.8 GW from 112 projects. 2035 is the furthest expected year of the four grids with a page here.

Planned CAISO projects by expected in-service year
Expected in-service yearProjectsCapacityShare of capacity
Before 2026, still listed as planned 41 6.1 GW 3.3%
2026 152 14.8 GW 7.9%
2027 166 26.6 GW 14.3%
2028 112 39.8 GW 21.4%
2029 97 26.3 GW 14.1%
2030 74 19.8 GW 10.6%
2031 94 31.1 GW 16.7%
2032 17 8.6 GW 4.6%
2033 17 8.7 GW 4.7%
2034 8 3.8 GW 2%
2035 2 556.3 MW 0.3%
All planned projects 780 186.2 GW 100%

The five largest planned CAISO entries

The five largest planned CAISO entries run from 1.2 GW to 2.3 GW, against an average of 239.3 MW among planned entries that state a capacity. Names are shown as the source lists them. An entry can be a single unit or one phase of a larger site, so each figure describes that entry alone.

Large planned CAISO entries by capacity
Entry nameCapacity
Atlas Complex 2.3 GW
Holman 1.5 GW
Sanborn Hybrid 3 1.4 GW
Chokecherry and Sierra Madre Wind 1.3 GW
Wingtip Solar 1 1.2 GW

What the database adds for CAISO

A developer is attributed on 42.2% of planned CAISO projects (329 of 780) and 9.9% of operating ones. That is the second-highest planned share of the four grids with a page here.

Filter the CAISO rows by technology or state, then export the result as CSV or Excel.

Source. CAISO interconnection queue and U.S. Energy Information Administration Form EIA-860M, compiled by FieldProspects.