Somervell County, Texas
Somervell County, Texas has 1.2 GW of data centers on record, planned to operating, across 18 records, against 2.4 GW of generation operating inside the county. The queue adds 836.4 MW of planned generation across 3 projects. That is 1.1% of Texas's data center MW.
Somervell County and its neighbors
Counties shaded by data center MW on record, planned to operating. 4 of its 4 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
of the generation operating in the county is matched by data center MW on record: 1.2 GW of data centers against 2.4 GW of plants, with 836.4 MW more planned.
Data centers by status
18 records, 1.2 GW
The data center pipeline
18 records list a year online or expected, from 2028 to 2032. The largest expected additions are 260 MW listed for 2028 and 260 MW for 2030.
Data center MW by year online or expected
Records not cancelled, by listed year. 2026 onward is planned or under construction.
View as table
| Year | Records | MW |
|---|---|---|
| 2028 | 4 | 260 |
| 2029 | 4 | 260 |
| 2030 | 4 | 260 |
| 2031 | 4 | 260 |
| 2032 | 2 | 130 |
Who is building in Somervell
Data center developers by MW on record. Top 1 of 1.
View as table
| Developer | Sites | MW |
|---|---|---|
| Amazon | 18 | 1,170 |
Power generation in the county
2 plants operate inside Somervell County, 2.4 GW of nuclear. The queue adds 836.4 MW across 3 projects.
Operating and planned generation by technology
MW in Somervell County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Nuclear | Operating | 2 | 2,430 |
| Natural Gas | Planned | 1 | 495.3 |
| Solar | Planned | 2 | 341.1 |
Planned generation by listed in-service year
MW. Years before 2026 are past due.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2027 | 2 | 341.1 |
| 2028 | 0 | 0 |
| 2029 | 1 | 495.3 |
Somervell County against its neighbors
Hood County has the most data center MW among the neighbors, 4.4 GW, more than Somervell County. 3 of the 4 have more generation operating than data center MW on record.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| Hood County | 2 | 961 | 1.7x | ||
| Somervell County this page | 18 | 836 | 0.48x | ||
| Bosque County | 1 | 599 | 0.3x | ||
| Johnson County | 0 | 629 | 0x | ||
| Erath County | 0 | 869 | 0x |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
5 counties shownEvery record in Somervell County
Campus or project name, developer, status, MW, year and the developer’s contacts, for all 23 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for Somervell County
We email you when a data center or power project in Somervell County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.
Open every campus, project and contact in Somervell County.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.