Bosque County, Texas
Bosque County, Texas has 400 MW of data centers on record, planned to operating, across 1 record, against 1.3 GW of generation operating inside the county. The queue adds 599.4 MW of planned generation across 5 projects. That is 0.4% of Texas's data center MW.
Bosque County and its neighbors
Counties shaded by data center MW on record, planned to operating. 7 of its 7 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
of the generation operating in the county is matched by data center MW on record: 400 MW of data centers against 1.3 GW of plants, with 599.4 MW more planned.
Data centers by status
1 record, 400 MW
The data center pipeline
1 record list a year online or expected, from 2026 to 2026. The largest expected additions are 400 MW listed for 2026.
Data center MW by year online or expected
Records not cancelled, by listed year. 2026 onward is planned or under construction.
View as table
| Year | Records | MW |
|---|---|---|
| 2026 | 1 | 400 |
Who is building in Bosque
Data center developers by MW on record. Top 1 of 1.
View as table
| Developer | Sites | MW |
|---|---|---|
| CyrusOne | 1 | 400 |
Power generation in the county
12 plants operate inside Bosque County, 1.3 GW. The queue adds 599.4 MW across 5 projects.
Operating and planned generation by technology
MW in Bosque County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Solar | Operating | 5 | 490.9 |
| Solar | Planned | 4 | 391.8 |
| Natural Gas | Operating | 5 | 807 |
| Battery Storage | Planned | 1 | 207.6 |
| Hydro | Operating | 2 | 41.8 |
Planned generation by listed in-service year
MW. Years before 2026 are past due.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2027 | 4 | 391.8 |
| 2028 | 0 | 0 |
| 2029 | 0 | 0 |
| 2030 | 1 | 207.6 |
Bosque County against its neighbors
Hill County has the most data center MW among the neighbors, 7.2 GW, more than Bosque County. 6 of the 7 have more generation operating than data center MW on record.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| Hill County | 5 | 9,693 | 4.7x | ||
| McLennan County | 3 | 3,913 | 0.95x | ||
| Somervell County | 18 | 836 | 0.48x | ||
| Bosque County this page | 1 | 599 | 0.3x | ||
| Johnson County | 0 | 629 | 0x | ||
| Erath County | 0 | 869 | 0x | ||
| Hamilton County | 0 | 10 | 0x | ||
| Coryell County | 0 | 102 | 0x |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
8 counties shownWhat changed since June 4, 2026
1 project in Bosque County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.
Every change in Bosque County
Project, what changed, technology, MW and the dates that moved, for all 1 change.
| Project | Change | Technology | MW | Previous date | New date |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.
Every record in Bosque County
Campus or project name, developer, status, MW, year and the developer’s contacts, for all 18 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for Bosque County
We email you when a data center or power project in Bosque County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.
Open every campus, project and contact in Bosque County.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.