Falls County, Texas
Falls County, Texas has 21 power projects in the FieldProspects database: 7 operating plants totaling 940.6 MW and 14 planned projects totaling 2 GW. No data center record lists the county. Solar leads with 2.5 GW across 13 projects. 2 planned projects are past their listed in-service date.
Falls County and its neighbors
Counties shaded by data center MW on record, planned to operating. 5 of its 5 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
more planned than operating generation in Falls County. 14 projects in the queue would add 2 GW to the 940.6 MW operating today, and 2 of them are past their listed in-service date.
Technology mix
21 projects, 2.9 GW planned and operating
Power generation in the county
7 plants operate inside Falls County, 940.6 MW of solar and battery storage. The queue adds 2 GW across 14 projects, and 2 of them are past their listed in-service date.
Operating and planned generation by technology
MW in Falls County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Solar | Operating | 5 | 708.8 |
| Solar | Planned | 8 | 1,750.5 |
| Battery Storage | Operating | 2 | 231.8 |
| Battery Storage | Planned | 5 | 60 |
| Wind | Planned | 1 | 198.7 |
Planned generation by listed in-service year
MW. Years before 2026 are past due.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2025 | 2 | 508 |
| 2026 | 3 | 644.6 |
| 2027 | 2 | 301.6 |
| 2028 | 4 | 190.6 |
| 2029 | 3 | 364.4 |
Falls County against its neighbors
Milam County has the most data center MW among the neighbors, 1.6 GW. 4 of the 5 have more generation operating than data center MW on record.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| Milam County | 3 | 9,986 | 1.8x | ||
| McLennan County | 3 | 3,913 | 0.95x | ||
| Bell County | 10 | 4,001 | 0.08x | ||
| Limestone County | 0 | 1,466 | 0x | ||
| Robertson County | 0 | 4,489 | 0x | ||
| Falls County this page | 0 | 2,009 | 0x |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
6 counties shownWhat changed since June 4, 2026
4 projects in Falls County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.
Every change in Falls County
Project, what changed, technology, MW and the dates that moved, for all 4 changes.
| Project | Change | Technology | MW | Previous date | New date |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.
Every record in Falls County
Project name, developer, status, MW, in-service year and the developer’s contacts, for all 21 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for Falls County
We email you when a data center or power project in Falls County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.
Open every campus, project and contact in Falls County.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.