Milam County, Texas

Milam County, Texas has 1.6 GW of data centers on record, planned to operating, across 3 records, against 890 MW of generation operating inside the county. The queue adds 10 GW of planned generation across 38 projects, 2 of them past their listed in-service date.

Data as of Grid region: ERCOTRefreshed monthly
1.6GW
data centers, planned to operating
3
data center records, not cancelled
1.6%
of Texas's data center MW
890MW
operating generation, 6 solar projects
10GW
planned generation, 38 projects
2
data center developers active here
Map

Milam County and its neighbors

Counties shaded by data center MW on record, planned to operating. 4 of its 6 neighboring counties have pages of their own. The rest are in the member database.

Falls no data centers Bell 235.6 MW Williamson 890 MW Burleson Lee Robertson no data centers Milam 1.6 GW
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
1.8times

more data center MW than operating generation in the county. Milam County's own plants cover 54.3% of the load on record, and the planned pipeline adds 10 GW.

Data centers, planned to operating1.6 GW
Operating generation890 MW
Planned generation10 GW

Data centers by status

3 records, 1.6 GW

Operating700 MW1 record, 43%
Under construction938.5 MW2 records, 57%
Who owns each of the 3 records?Campus names, developers and contacts are for members.See what members get

The data center pipeline

3 records list a year online or expected, from 2020 to 2028. The largest expected additions are 554.6 MW listed for 2028 and 383.9 MW for 2027.

Figure 1

Data center MW by year online or expected

Records not cancelled, by listed year. 2026 onward is planned or under construction.

Through 20252026 and later
0200400600800 Snapshot year 700 2020 2021 2022 2023 2024 2025 2026 384 2027 555 2028
View as table
YearRecordsMW
20201700
202100
202200
202300
202400
202500
202600
20271384
20281555
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026. 3 records with a year
Figure 2

Who is building in Milam

Data center developers by MW on record. Top 2 of 2.

SB Energy 938.5 MW 2 sites
Riot Platforms 700 MW 1 site
View as table
DeveloperSitesMW
SB Energy2939
Riot Platforms1700
Members see all 2 developers, each campus they own here, and the people who run their site selection and energy procurement.
Aggregates only. Campus names are for members.

Power generation in the county

6 plants operate inside Milam County, 890 MW of solar. The queue adds 10 GW across 38 projects, and 2 of them are past their listed in-service date.

Figure 3

Operating and planned generation by technology

MW in Milam County

OperatingPlanned
SolarOperating 890 MW 6 projects
SolarPlanned 4.7 GW 20 projects
Battery StoragePlanned 3.2 GW 16 projects
Natural GasPlanned 2.1 GW 2 projects
View as table
TechnologyStatusProjectsMW
SolarOperating6890
SolarPlanned204,665.6
Battery StoragePlanned163,183
Natural GasPlanned22,137.6
Operating: 890 MW. Planned: 10 GW. Even if every planned project is built, county generation would reach 10.9 GW against 1.6 GW of data centers.
Source: ISO queues and EIA-860M, via FieldProspects
Figure 4

Planned generation by listed in-service year

MW. Years before 2026 are past due.

Past dueDue 2026 or later
01k2k3k4k Snapshot year 365 2025 3,450 2026 1,517 2027 2,704 2028 1,950 2029
View as table
YearPlanned projectsMW
20252365.5
2026133,449.9
202791,516.6
202892,703.8
202951,950.4
2 projects, 365.5 MW, were due before 2026

Milam County against its neighbors

Williamson County has the most data center MW among the neighbors, 890 MW, 54% of Milam County's. 3 of the 4 have more generation operating than data center MW on record.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
Milam County this page 3
1,639
890
9,986 1.8x
Williamson County 10
890
214
449 4.2x
Bell County 10
236
2,819
4,001 0.08x
Robertson County 0
0
2,395
4,489 0x
Falls County 0
0
941
2,009 0x

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

5 counties shown

What changed since June 4, 2026

15 projects in Milam County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.

Open the change feed
0
added to a queue, 0 MW
2
came online, started construction or signed an interconnection agreement, 382.5 MW
4
cancelled, dropped or went inactive, 908.7 MW
9
slipped their in-service date, 1.4 GW

Every change in Milam County

Project, what changed, technology, MW and the dates that moved, for all 15 changes.

Members only
County: Milam County, TXSince June 4, 2026 15 changes
ProjectChangeTechnologyMWPrevious dateNew date
15 changes behind this preview

Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.

Request access

Every record in Milam County

Campus or project name, developer, status, MW, year and the developer’s contacts, for all 47 records. Filter, sort and export to Excel.

Members only
County: Milam County, TXStatus: all except cancelledSort: MW, largest first 47 records
Project or campusDeveloperStatusMWYearContacts
47 records and 12.5 GW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Milam County

We email you when a data center or power project in Milam County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Milam County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.