Ellis County, Texas has 5.3 GW of data centers on record, planned to operating, across 52 records, against 2.5 GW of generation operating inside the county. The queue adds 6.4 GW of planned generation across 29 projects. That is 5% of Texas's data center MW.

Data as of Grid region: ERCOTRefreshed monthly
5.3GW
data centers, planned to operating
52
data center records, not cancelled
5%
of Texas's data center MW
2.5GW
operating generation, 11 projects
6.4GW
planned generation, 29 projects
6
data center developers active here
Map

Ellis County and its neighbors

Counties shaded by data center MW on record, planned to operating. 7 of its 7 neighboring counties have pages of their own. The rest are in the member database.

Hill 7.2 GW Ellis 5.3 GW Kaufman 200 MW Tarrant 1.4 GW Dallas 4 GW Navarro no data centers Henderson no data centers Johnson no data centers
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
2.1times

more data center MW than operating generation in the county. Ellis County's own plants cover 47.7% of the load on record, and the planned pipeline adds 6.4 GW.

Data centers, planned to operating5.3 GW
Operating generation2.5 GW
Planned generation6.4 GW

Data centers by status

52 records, 5.3 GW

Operating837.8 MW15 records, 16%
Under construction504.8 MW6 records, 10%
Planned3.9 GW31 records, 75%
Who owns each of the 52 records?Campus names, developers and contacts are for members.See what members get

The data center pipeline

26 records list a year online or expected, from 2020 to 2028. The largest expected additions are 583.8 MW listed for 2026 and 411 MW for 2028. 26 records list no year.

Figure 1

Data center MW by year online or expected

Records not cancelled, by listed year. 2026 onward is planned or under construction.

Through 20252026 and later
0200400600 Snapshot year 2020 2021 2022 2023 2024 197 2025 584 2026 2027 411 2028
View as table
YearRecordsMW
20203158
202100
202200
2023290
20243135
20253197
20268584
20272179
20285411
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026. 26 records with a year; 26 without are left out
Figure 2

Who is building in Ellis

Data center developers by MW on record. Top 6 of 6.

PowerHouse 1.8 GW 24 sites
Provident Data Centers 1.8 GW 1 site
DataBank 672 MW 8 sites
Google 549.1 MW 6 sites
Compass Datacenters 457.5 MW 12 sites
Cawley Partners 0 MW 1 site
View as table
DeveloperSitesMW
PowerHouse241,800
Provident Data Centers11,800
DataBank8672
Google6549
Compass Datacenters12458
Cawley Partners10
Members see all 6 developers, each campus they own here, and the people who run their site selection and energy procurement.
Aggregates only. Campus names are for members.

Power generation in the county

11 plants operate inside Ellis County, 2.5 GW. The queue adds 6.4 GW across 29 projects.

Figure 3

Operating and planned generation by technology

MW in Ellis County

OperatingPlanned
Battery StorageOperating 150 MW 1 project
Battery StoragePlanned 3.4 GW 13 projects
Natural GasOperating 2.2 GW 8 projects
Natural GasPlanned 897.9 MW 5 projects
SolarOperating 214.7 MW 2 projects
SolarPlanned 2.1 GW 10 projects
OtherPlanned 50 MW 1 project
View as table
TechnologyStatusProjectsMW
Battery StorageOperating1150
Battery StoragePlanned133,403.8
Natural GasOperating82,152
Natural GasPlanned5897.9
SolarOperating2214.7
SolarPlanned102,089.4
OtherPlanned150
Operating: 2.5 GW. Planned: 6.4 GW. Even if every planned project is built, county generation would reach 9 GW against 5.3 GW of data centers.
Source: ISO queues and EIA-860M, via FieldProspects
Figure 4

Planned generation by listed in-service year

MW. Years before 2026 are past due.

Past dueDue 2026 or later
01k2k3k4k Snapshot year 126 2026 1,099 2027 969 2028 3,187 2029 1,060 2030
View as table
YearPlanned projectsMW
20261125.7
202781,099.3
20287969.1
2029103,187.4
203031,059.6
No planned project is past its listed year

Ellis County against its neighbors

Hill County has the most data center MW among the neighbors, 7.2 GW, more than Ellis County. 5 of the 7 have more generation operating than data center MW on record.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
Hill County 5
7,230
1,543
9,693 4.7x
Ellis County this page 52
5,279
2,517
6,441 2.1x
Dallas County 68
4,041
2,070
2,025 2x
Tarrant County 29
1,432
1,484
792 0.97x
Kaufman County 1
200
2,196
2,926 0.09x
Navarro County 0
0
1,215
7,021 0x
Henderson County 0
0
546
1,301 0x
Johnson County 0
0
283
629 0x

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

8 counties shown

What changed since June 4, 2026

14 projects in Ellis County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.

Open the change feed
4
added to a queue, 1.4 GW
2
came online, started construction or signed an interconnection agreement, 394 MW
3
cancelled, dropped or went inactive, 491.2 MW
5
slipped their in-service date, 449.4 MW

Every change in Ellis County

Project, what changed, technology, MW and the dates that moved, for all 14 changes.

Members only
County: Ellis County, TXSince June 4, 2026 14 changes
ProjectChangeTechnologyMWPrevious dateNew date
14 changes behind this preview

Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.

Request access

Every record in Ellis County

Campus or project name, developer, status, MW, year and the developer’s contacts, for all 92 records. Filter, sort and export to Excel.

Members only
County: Ellis County, TXStatus: all except cancelledSort: MW, largest first 92 records
Project or campusDeveloperStatusMWYearContacts
92 records and 14.2 GW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Ellis County

We email you when a data center or power project in Ellis County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Ellis County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.