St Lawrence County, New York
St Lawrence County, New York has 4.5 GW of data centers on record, planned to operating, across 6 records, against 1.4 GW of generation operating inside the county. The queue adds 972.1 MW of planned generation across 6 projects. That is 45.3% of New York's data center MW.
St Lawrence County and its neighbors
Counties shaded by data center MW on record, planned to operating. 4 of its 5 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
more data center MW than operating generation in the county. St Lawrence County's own plants cover 30.9% of the load on record, and the planned pipeline adds 972.1 MW.
Data centers by status
6 records, 4.5 GW
The data center pipeline
None of the 6 records lists a year online or expected, so the pipeline is shown by developer only.
Who is building in St Lawrence
Data center developers by MW on record. Top 6 of 6.
View as table
| Developer | Sites | MW |
|---|---|---|
| St. Lawrence Infrastructure LLC | 1 | 2,795 |
| Arconic Corporation | 1 | 933 |
| North Country Colocation Services | 1 | 435 |
| American Data Center Partners LLC | 1 | 250 |
| Sabey Data Center Properties | 1 | 120 |
| Petawatt Holdings | 1 | 0 |
Power generation in the county
116 plants operate inside St Lawrence County, 1.4 GW. The queue adds 972.1 MW across 6 projects.
Operating and planned generation by technology
MW in St Lawrence County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Hydro | Operating | 82 | 1,155.3 |
| Solar | Operating | 30 | 113.4 |
| Solar | Planned | 5 | 732.1 |
| Solar + Storage (Hybrid) | Planned | 1 | 240 |
| Natural Gas | Operating | 3 | 129 |
| Oil | Operating | 1 | 2 |
Planned generation by listed in-service year
MW. Years before 2026 are past due.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2027 | 1 | 12.1 |
| 2028 | 4 | 860 |
| 2029 | 1 | 100 |
St Lawrence County against its neighbors
Herkimer County has the most data center MW among the neighbors, 500 MW, 11% of St Lawrence County's. 3 of the 4 have more generation operating than data center MW on record.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| St Lawrence County this page | 6 | 972 | 3.2x | ||
| Herkimer County | 1 | 533 | 3.6x | ||
| Lewis County | 0 | 125 | 0x | ||
| Jefferson County | 0 | 998 | 0x | ||
| Franklin County | 0 | 2,575 | 0x |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
5 counties shownWhat changed since June 4, 2026
11 projects in St Lawrence County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.
Every change in St Lawrence County
Project, what changed, technology, MW and the dates that moved, for all 11 changes.
| Project | Change | Technology | MW | Previous date | New date |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.
Every record in St Lawrence County
Campus or project name, developer, status, MW, year and the developer’s contacts, for all 128 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for St Lawrence County
We email you when a data center or power project in St Lawrence County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.
Open every campus, project and contact in St Lawrence County.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.