FieldProspects

Wilson County, Texas

Wilson County, Texas has 26 power projects in the FieldProspects database: 7 operating plants totaling 7 MW and 19 planned projects totaling 5.1 GW. No data center record lists the county. Solar leads with 2.4 GW across 14 projects. No planned project is past its listed in-service date.

Data as of Grid region: ERCOTRefreshed monthly
26
power projects, planned and operating
5.1GW
planned generation, 19 projects
7MW
operating generation, 7 solar projects
0
planned projects past their listed in-service date
Map

Wilson County and its neighbors

Counties shaded by data center MW on record, planned to operating. 5 of its 5 neighboring counties have pages of their own. The rest are in the member database.

Atascosa no data centers Wilson no data centers Gonzales no data centers Karnes no data centers Guadalupe no data centers Bexar 2.9 GW
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
733times

more planned than operating generation in Wilson County. 19 projects in the queue would add 5.1 GW to the 7 MW operating today.

Operating generation7 MW
Planned generation5.1 GW

Technology mix

26 projects, 5.1 GW planned and operating

Solar2.4 GW14 projects, 47%
Battery Storage2.3 GW11 projects, 45%
Natural Gas402.9 MW1 project, 8%
Which companies own these 26 projects?Project names, developers and contacts are for members.See what members get

Power generation in the county

7 plants operate inside Wilson County, 7 MW of solar. The queue adds 5.1 GW across 19 projects.

Figure 1

Operating and planned generation by technology

MW in Wilson County

OperatingPlanned
SolarOperating 7 MW 7 projects
SolarPlanned 2.4 GW 7 projects
Battery StoragePlanned 2.3 GW 11 projects
Natural GasPlanned 402.9 MW 1 project
View as table
TechnologyStatusProjectsMW
SolarOperating77
SolarPlanned72,431.3
Battery StoragePlanned112,298.5
Natural GasPlanned1402.9
Operating: 7 MW. Planned: 5.1 GW. If every planned project is built, county generation would reach 5.1 GW.
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026.
Figure 2

Planned generation by listed in-service year

MW. Years before 2026 are past due.

Past dueDue 2026 or later
05001k1.5k2k Snapshot year 203 2026 1,802 2027 1,897 2028 1,230 2029
View as table
YearPlanned projectsMW
20261203.2
202741,802
202871,897.4
202971,230.2
No planned project is past its listed year

Wilson County against its neighbors

Bexar County has the most data center MW among the neighbors, 2.9 GW. 5 of the 5 have more generation operating than data center MW on record.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
Bexar County 41
2,906
4,969
5,920 0.58x
Guadalupe County 0
0
2,651
4,064 0x
Atascosa County 0
0
420
1,782 0x
Karnes County 0
0
30
1,876 0x
Wilson County this page 0
0
7
5,133 0x
Gonzales County 0
0
5
1,235 0x

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

6 counties shown

Every record in Wilson County

Project name, developer, status, MW, in-service year and the developer’s contacts, for all 26 records. Filter, sort and export to Excel.

Members only
County: Wilson County, TXStatus: all except cancelledSort: MW, largest first 26 records
Project or campusDeveloperStatusMWYearContacts
26 records and 5.1 GW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Wilson County

We email you when a data center or power project in Wilson County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Wilson County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.