Glasscock County, Texas
Glasscock County, Texas has 28 power projects in the FieldProspects database: 6 operating plants totaling 743 MW and 22 planned projects totaling 4 GW. No data center record lists the county. Wind leads with 1.9 GW across 13 projects. No planned project is past its listed in-service date.
Glasscock County and its neighbors
Counties shaded by data center MW on record, planned to operating. 5 of its 5 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
more planned than operating generation in Glasscock County. 22 projects in the queue would add 4 GW to the 743 MW operating today.
Technology mix
28 projects, 4.8 GW planned and operating
Power generation in the county
6 plants operate inside Glasscock County, 743 MW of wind and battery storage. The queue adds 4 GW across 22 projects.
Operating and planned generation by technology
MW in Glasscock County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Wind | Operating | 5 | 733.1 |
| Wind | Planned | 8 | 1,135.2 |
| Battery Storage | Operating | 1 | 9.9 |
| Battery Storage | Planned | 9 | 1,308 |
| Solar | Planned | 4 | 1,208.5 |
| Natural Gas | Planned | 1 | 370.1 |
Planned generation by listed in-service year
MW. Years before 2026 are past due.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2026 | 6 | 642.3 |
| 2027 | 3 | 712.2 |
| 2028 | 12 | 2,461.8 |
| 2029 | 1 | 205.5 |
Glasscock County against its neighbors
Midland County has the most data center MW among the neighbors, 150 MW. 4 of the 5 have more generation operating than data center MW on record.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| Midland County | 2 | 876 | 1.1x | ||
| Sterling County | 0 | 1,644 | 0x | ||
| Glasscock County this page | 0 | 4,022 | 0x | ||
| Howard County | 0 | 2,680 | 0x | ||
| Reagan County | 0 | 618 | 0x | ||
| Martin County | 0 | 492 | 0x |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
6 counties shownWhat changed since June 4, 2026
10 projects in Glasscock County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.
Every change in Glasscock County
Project, what changed, technology, MW and the dates that moved, for all 10 changes.
| Project | Change | Technology | MW | Previous date | New date |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.
Every record in Glasscock County
Project name, developer, status, MW, in-service year and the developer’s contacts, for all 28 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for Glasscock County
We email you when a data center or power project in Glasscock County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.
Open every campus, project and contact in Glasscock County.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.