Clearfield County, Pennsylvania has 31 power projects in the FieldProspects database: 9 operating plants totaling 672 MW and 22 planned projects totaling 2.4 GW. No data center record lists the county. Solar leads with 1.7 GW across 20 projects. 2 planned projects are past their listed in-service date.

Data as of Grid region: PJM InterconnectionRefreshed monthly
31
power projects, planned and operating
2.4GW
planned generation, 22 projects
672MW
operating generation, 9 projects
2
planned projects past their listed in-service date
Map

Clearfield County and its neighbors

Counties shaded by data center MW on record, planned to operating. 5 of its 8 neighboring counties have pages of their own. The rest are in the member database.

Jefferson Cambria no data centers Cameron Elk no data centers Blair no data centers Indiana 2.7 GW Centre no data centers Clearfield no data centers Clinton
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
3.5times

more planned than operating generation in Clearfield County. 22 projects in the queue would add 2.4 GW to the 672 MW operating today, and 2 of them are past their listed in-service date.

Operating generation672 MW
Planned generation2.4 GW

Technology mix

31 projects, 3 GW planned and operating

Solar1.7 GW20 projects, 55%
Natural Gas626 MW4 projects, 21%
Battery Storage400 MW1 project, 13%
2 other technologies335.7 MW6 projects, 11%
Which companies own these 31 projects?Project names, developers and contacts are for members.See what members get

Power generation in the county

9 plants operate inside Clearfield County, 672 MW. The queue adds 2.4 GW across 22 projects, and 2 of them are past their listed in-service date.

Figure 1

Operating and planned generation by technology

MW in Clearfield County

OperatingPlanned
SolarOperating 40 MW 2 projects
SolarPlanned 1.6 GW 18 projects
Natural GasOperating 626 MW 4 projects
Battery StoragePlanned 400 MW 1 project
WindPlanned 329.7 MW 3 projects
OilOperating 6 MW 3 projects
View as table
TechnologyStatusProjectsMW
SolarOperating240
SolarPlanned181,620.7
Natural GasOperating4626
Battery StoragePlanned1400
WindPlanned3329.7
OilOperating36
Operating: 672 MW. Planned: 2.4 GW. If every planned project is built, county generation would reach 3 GW.
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026.
Figure 2

Planned generation by listed in-service year

MW. Years before 2026 are past due. 2 planned projects list no date and are left out.

Past dueDue 2026 or later
05001k1.5k Snapshot year 36 2021 2022 2023 2024 2025 220 2026 66 2027 425 2028 1,227 2029 250 2030
View as table
YearPlanned projectsMW
2021236
202200
202300
202400
202500
20262219.8
2027865.5
20283424.6
202941,226.6
20301250
2 projects, 36 MW, were due before 2026

Clearfield County against its neighbors

Indiana County has the most data center MW among the neighbors, 2.7 GW. 4 of the 5 have more generation operating than data center MW on record.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
Indiana County 36
2,700
2,572
11,363 1x
Cambria County 0
0
1,834
170 0x
Clearfield County this page 0
0
672
2,350 0x
Blair County 0
0
252
20 0x
Elk County 0
0
54
6 0x
Centre County 0
0
28
853 0x

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

6 counties shown

What changed since June 4, 2026

16 projects in Clearfield County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.

Open the change feed
6
added to a queue, 15 MW
0
came online, started construction or signed an interconnection agreement, 0 MW
7
cancelled, dropped or went inactive, 374.9 MW
3
slipped their in-service date, 435.1 MW

Every change in Clearfield County

Project, what changed, technology, MW and the dates that moved, for all 16 changes.

Members only
County: Clearfield County, PASince June 4, 2026 16 changes
ProjectChangeTechnologyMWPrevious dateNew date
16 changes behind this preview

Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.

Request access

Every record in Clearfield County

Project name, developer, status, MW, in-service year and the developer’s contacts, for all 31 records. Filter, sort and export to Excel.

Members only
County: Clearfield County, PAStatus: all except cancelledSort: MW, largest first 31 records
Project or campusDeveloperStatusMWYearContacts
31 records and 3 GW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Clearfield County

We email you when a data center or power project in Clearfield County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Clearfield County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.