FieldProspects

Kay County, Oklahoma

Kay County, Oklahoma has 15 power projects in the FieldProspects database: 10 operating plants totaling 1.4 GW and 5 planned projects totaling 519.6 MW. No data center record lists the county. Wind leads with 1.1 GW across 6 projects. No planned project is past its listed in-service date.

Data as of Grid region: Southwest Power Pool (SPP)Refreshed monthly
15
power projects, planned and operating
519.6MW
planned generation, 5 projects
1.4GW
operating generation, 10 projects
0
planned projects past their listed in-service date
Map

Kay County and its neighbors

Counties shaded by data center MW on record, planned to operating. 3 of its 4 neighboring counties have pages of their own. The rest are in the member database.

Garfield no data centers Kay no data centers Osage 0 MW Noble no data centers Grant
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
38%

of the county's operating generation is in the queue as new capacity: 519.6 MW planned across 5 projects against 1.4 GW operating.

Operating generation1.4 GW
Planned generation519.6 MW

Technology mix

15 projects, 1.9 GW planned and operating

Wind1.1 GW6 projects, 60%
Natural Gas359.3 MW5 projects, 19%
Battery Storage352 MW3 projects, 19%
One other technology37 MW1 project, 2%
Which companies own these 15 projects?Project names, developers and contacts are for members.See what members get

Power generation in the county

10 plants operate inside Kay County, 1.4 GW. The queue adds 519.6 MW across 5 projects.

Figure 1

Operating and planned generation by technology

MW in Kay County

OperatingPlanned
WindOperating 1.1 GW 5 projects
WindPlanned 64.6 MW 1 project
Natural GasOperating 256.3 MW 4 projects
Natural GasPlanned 103 MW 1 project
Battery StoragePlanned 352 MW 3 projects
HydroOperating 37 MW 1 project
View as table
TechnologyStatusProjectsMW
WindOperating51,065.1
WindPlanned164.6
Natural GasOperating4256.3
Natural GasPlanned1103
Battery StoragePlanned3352
HydroOperating137
Operating: 1.4 GW. Planned: 519.6 MW. If every planned project is built, county generation would reach 1.9 GW.
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026.
Figure 2

Planned generation by listed in-service year

MW. Years before 2026 are past due.

Past dueDue 2026 or later
0100200300400 352 2027 65 2028 103 2029
View as table
YearPlanned projectsMW
20273352
2028164.6
20291103
No planned project is past its listed year

Kay County against its neighbors

None of the 3 neighboring counties with a page lists a data center record. Garfield County has the most operating generation among them, 1.7 GW.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
Garfield County 0
0
1,721
0 0x
Noble County 0
0
1,656
426 0x
Kay County this page 0
0
1,358
520 0x
Osage County 2
0
163
0 0x

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

4 counties shown

Every record in Kay County

Project name, developer, status, MW, in-service year and the developer’s contacts, for all 15 records. Filter, sort and export to Excel.

Members only
County: Kay County, OKStatus: all except cancelledSort: MW, largest first 15 records
Project or campusDeveloperStatusMWYearContacts
15 records and 1.9 GW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Kay County

We email you when a data center or power project in Kay County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Kay County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.