Cumberland County, New Jersey
Cumberland County, New Jersey has 300 MW of data centers on record, planned to operating, across 2 records, against 555.1 MW of generation operating inside the county. The queue adds 168 MW of planned generation across 4 projects, 1 of them past its listed in-service date.
Cumberland County and its neighbors
Counties shaded by data center MW on record, planned to operating. 4 of its 4 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
of the generation operating in the county is matched by data center MW on record: 300 MW of data centers against 555.1 MW of plants, with 168 MW more planned.
Data centers by status
2 records, 300 MW
The data center pipeline
2 records list a year online or expected, from 2026 to 2027. The largest expected additions are 200 MW listed for 2027 and 100 MW for 2026.
Data center MW by year online or expected
Records not cancelled, by listed year. 2026 onward is planned or under construction.
View as table
| Year | Records | MW |
|---|---|---|
| 2026 | 1 | 100 |
| 2027 | 1 | 200 |
Who is building in Cumberland
Data center developers by MW on record. Top 1 of 1.
View as table
| Developer | Sites | MW |
|---|---|---|
| DataOne | 2 | 300 |
Power generation in the county
30 plants operate inside Cumberland County, 555.1 MW. The queue adds 168 MW across 4 projects, and one of them is past its listed in-service date.
Operating and planned generation by technology
MW in Cumberland County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Natural Gas | Operating | 5 | 485.2 |
| Battery Storage | Planned | 2 | 130 |
| Solar | Operating | 22 | 65.1 |
| Solar | Planned | 2 | 38 |
| Landfill Gas | Operating | 3 | 4.8 |
Planned generation by listed in-service year
MW. Years before 2026 are past due. 1 planned project lists no date and is left out.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2023 | 1 | 19 |
| 2024 | 0 | 0 |
| 2025 | 0 | 0 |
| 2026 | 0 | 0 |
| 2027 | 0 | 0 |
| 2028 | 2 | 130 |
Cumberland County against its neighbors
None of the 4 neighboring counties with a page lists a data center record. Salem County has the most operating generation among them, 3.7 GW.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| Cumberland County this page | 2 | 168 | 0.54x | ||
| Salem County | 0 | 5,775 | 0x | ||
| Gloucester County | 0 | 415 | 0x | ||
| Atlantic County | 0 | 290 | 0x | ||
| Cape May County | 0 | 20 | 0x |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
5 counties shownWhat changed since June 4, 2026
1 project in Cumberland County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.
Every change in Cumberland County
Project, what changed, technology, MW and the dates that moved, for all 1 change.
| Project | Change | Technology | MW | Previous date | New date |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.
Every record in Cumberland County
Campus or project name, developer, status, MW, year and the developer’s contacts, for all 36 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for Cumberland County
We email you when a data center or power project in Cumberland County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.
Open every campus, project and contact in Cumberland County.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.