Prince Edward County, Virginia
Prince Edward County, Virginia has 300 MW of data centers on record, planned to operating, across 2 records, against 10 MW of generation operating inside the county. The queue adds 566 MW of planned generation across 5 projects, 3 of them past their listed in-service date.
Prince Edward County and its neighbors
Counties shaded by data center MW on record, planned to operating. 5 of its 7 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
more data center MW than operating generation in the county. Prince Edward County's own plants cover 3.3% of the load on record, and the planned pipeline adds 566 MW.
Data centers by status
2 records, 300 MW
The data center pipeline
None of the 2 records lists a year online or expected, so the pipeline is shown by developer only.
Who is building in Prince Edward
Data center developers by MW on record. Top 2 of 2.
View as table
| Developer | Sites | MW |
|---|---|---|
| Avaio Digital Partners | 1 | 300 |
| Prince Edward County Industrial Development Authority | 1 | 0 |
Power generation in the county
3 plants operate inside Prince Edward County, 10 MW of solar. The queue adds 566 MW across 5 projects, and 3 of them are past their listed in-service date.
Operating and planned generation by technology
MW in Prince Edward County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Solar | Operating | 3 | 10 |
| Solar | Planned | 3 | 346 |
| Battery Storage | Planned | 2 | 220 |
Planned generation by listed in-service year
MW. Years before 2026 are past due. 2 planned projects list no date and are left out.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2024 | 2 | 190 |
| 2025 | 1 | 186 |
Prince Edward County against its neighbors
None of the 5 neighboring counties with a page lists a data center record. Buckingham County has the most operating generation among them, 598.8 MW.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| Prince Edward County this page | 2 | 566 | 30x | ||
| Buckingham County | 0 | 1,983 | 0x | ||
| Amelia County | 0 | 405 | 0x | ||
| Charlotte County | 0 | 2,909 | 0x | ||
| Cumberland County | 0 | 840 | no operating MW | ||
| Lunenburg County | 0 | 434 | no operating MW |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
6 counties shownWhat changed since June 4, 2026
4 projects in Prince Edward County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.
Every change in Prince Edward County
Project, what changed, technology, MW and the dates that moved, for all 4 changes.
| Project | Change | Technology | MW | Previous date | New date |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.
Every record in Prince Edward County
Campus or project name, developer, status, MW, year and the developer’s contacts, for all 10 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for Prince Edward County
We email you when a data center or power project in Prince Edward County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.
Open every campus, project and contact in Prince Edward County.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.