Powhatan County, Virginia
Powhatan County, Virginia has 365 MW of data centers on record, planned to operating, across 1 record, against 120 MW of generation operating inside the county. The queue adds 139.9 MW of planned generation across 3 projects, 1 of them past its listed in-service date.
Powhatan County and its neighbors
Counties shaded by data center MW on record, planned to operating. 4 of its 4 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
more data center MW than operating generation in the county. Powhatan County's own plants cover 32.9% of the load on record, and the planned pipeline adds 139.9 MW.
Data centers by status
1 record, 365 MW
The data center pipeline
None of the 1 record lists a year online or expected, so the pipeline is shown by developer only.
Who is building in Powhatan
Data center developers by MW on record. Top 1 of 1.
View as table
| Developer | Sites | MW |
|---|---|---|
| Province Group | 1 | 365 |
Power generation in the county
6 plants operate inside Powhatan County, 120 MW of solar and battery storage. The queue adds 139.9 MW across 3 projects, and one of them is past its listed in-service date.
Operating and planned generation by technology
MW in Powhatan County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Solar | Operating | 5 | 80 |
| Solar | Planned | 3 | 139.9 |
| Battery Storage | Operating | 1 | 40 |
Planned generation by listed in-service year
MW. Years before 2026 are past due. 1 planned project lists no date and is left out.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2023 | 1 | 20 |
| 2024 | 0 | 0 |
| 2025 | 0 | 0 |
| 2026 | 0 | 0 |
| 2027 | 1 | 99.9 |
Powhatan County against its neighbors
Goochland County has the most data center MW among the neighbors, 2.1 GW, more than Powhatan County. 1 of the 4 have more generation operating than data center MW on record.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| Goochland County | 2 | 40 | 420x | ||
| Chesterfield County | 16 | 3,085 | 1.9x | ||
| Powhatan County this page | 1 | 140 | 3x | ||
| Amelia County | 0 | 405 | 0x | ||
| Cumberland County | 0 | 840 | no operating MW |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
5 counties shownWhat changed since June 4, 2026
2 projects in Powhatan County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.
Every change in Powhatan County
Project, what changed, technology, MW and the dates that moved, for all 2 changes.
| Project | Change | Technology | MW | Previous date | New date |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.
Every record in Powhatan County
Campus or project name, developer, status, MW, year and the developer’s contacts, for all 10 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for Powhatan County
We email you when a data center or power project in Powhatan County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.