King George County, Virginia
King George County, Virginia has 2.4 GW of data centers on record, planned to operating, across 11 records, against 13.2 MW of generation operating inside the county. The queue adds 334 MW of planned generation across 3 projects. That is 4% of Virginia's data center MW.
King George County and its neighbors
Counties shaded by data center MW on record, planned to operating. 3 of its 4 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
more data center MW than operating generation in the county. King George County's own plants cover 0.6% of the load on record, and the planned pipeline adds 334 MW.
Data centers by status
11 records, 2.4 GW
The data center pipeline
None of the 11 records lists a year online or expected, so the pipeline is shown by developer only.
Who is building in King George
Data center developers by MW on record. Top 4 of 4.
View as table
| Developer | Sites | MW |
|---|---|---|
| Oasis Digital Properties | 1 | 1,200 |
| Amazon | 8 | 1,150 |
| Green Energy Ventures | 1 | 0 |
| Potomac Development Group | 1 | 0 |
Power generation in the county
4 plants operate inside King George County, 13.2 MW of landfill gas. The queue adds 334 MW across 3 projects.
Operating and planned generation by technology
MW in King George County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Solar | Planned | 2 | 234 |
| Battery Storage | Planned | 1 | 100 |
| Landfill Gas | Operating | 4 | 13.2 |
Planned generation by listed in-service year
MW. Years before 2026 are past due.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2028 | 1 | 100 |
| 2029 | 2 | 234 |
King George County against its neighbors
Stafford County has the most data center MW among the neighbors, 1.8 GW, 77% of King George County's. 1 of the 3 have more generation operating than data center MW on record.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| King George County this page | 11 | 334 | 178x | ||
| Stafford County | 36 | 5 | 517x | ||
| Caroline County | 22 | 2,246 | 1.9x | ||
| Westmoreland County | 0 | 112 | 0x |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
4 counties shownWhat changed since June 4, 2026
4 projects in King George County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.
Every change in King George County
Project, what changed, technology, MW and the dates that moved, for all 4 changes.
| Project | Change | Technology | MW | Previous date | New date |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.
Every record in King George County
Campus or project name, developer, status, MW, year and the developer’s contacts, for all 18 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for King George County
We email you when a data center or power project in King George County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.