Taylor County, Texas
Taylor County, Texas has 2.1 GW of data centers on record, planned to operating, across 11 records, against 991.1 MW of generation operating inside the county. The queue adds 3.8 GW of planned generation across 17 projects. That is 2% of Texas's data center MW.
Taylor County and its neighbors
Counties shaded by data center MW on record, planned to operating. 5 of its 5 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
more data center MW than operating generation in the county. Taylor County's own plants cover 47.2% of the load on record, and the planned pipeline adds 3.8 GW.
Data centers by status
11 records, 2.1 GW
The data center pipeline
10 records list a year online or expected, from 2025 to 2027. The largest expected additions are 900 MW listed for 2027 and 900 MW for 2026. 1 record list no year.
Data center MW by year online or expected
Records not cancelled, by listed year. 2026 onward is planned or under construction.
View as table
| Year | Records | MW |
|---|---|---|
| 2025 | 2 | 300 |
| 2026 | 6 | 900 |
| 2027 | 2 | 900 |
Who is building in Taylor
Data center developers by MW on record. Top 2 of 2.
View as table
| Developer | Sites | MW |
|---|---|---|
| Crusoe | 10 | 2,100 |
| Microsoft | 1 | 0 |
Power generation in the county
10 plants operate inside Taylor County, 991.1 MW. The queue adds 3.8 GW across 17 projects.
Operating and planned generation by technology
MW in Taylor County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Solar | Planned | 4 | 2,187.9 |
| Wind | Operating | 5 | 970.1 |
| Wind | Planned | 4 | 376.7 |
| Battery Storage | Operating | 2 | 19.8 |
| Battery Storage | Planned | 9 | 1,269.2 |
| Natural Gas | Operating | 3 | 1.2 |
Planned generation by listed in-service year
MW. Years before 2026 are past due.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2027 | 6 | 1,374.7 |
| 2028 | 5 | 648 |
| 2029 | 6 | 1,811.1 |
Taylor County against its neighbors
Nolan County has the most data center MW among the neighbors, 2 GW, 95% of Taylor County's. 4 of the 5 have more generation operating than data center MW on record.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| Taylor County this page | 11 | 3,834 | 2.1x | ||
| Nolan County | 2 | 5,272 | 0.72x | ||
| Callahan County | 0 | 1,986 | 0x | ||
| Jones County | 2 | 5,199 | 0x | ||
| Runnels County | 0 | 1,803 | 0x | ||
| Coleman County | 0 | 2,143 | no operating MW |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
6 counties shownWhat changed since June 4, 2026
8 projects in Taylor County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.
Every change in Taylor County
Project, what changed, technology, MW and the dates that moved, for all 8 changes.
| Project | Change | Technology | MW | Previous date | New date |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.
Every record in Taylor County
Campus or project name, developer, status, MW, year and the developer’s contacts, for all 38 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for Taylor County
We email you when a data center or power project in Taylor County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.
Open every campus, project and contact in Taylor County.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.