Haskell County, Texas has 630 MW of data centers on record, planned to operating, across 9 records, against 1.8 GW of generation operating inside the county. The queue adds 6.3 GW of planned generation across 25 projects. That is 0.6% of Texas's data center MW.

Data as of Grid region: ERCOTRefreshed monthly
630MW
data centers, planned to operating
9
data center records, not cancelled
0.6%
of Texas's data center MW
1.8GW
operating generation, 10 projects
6.3GW
planned generation, 25 projects
1
data center developers active here
Map

Haskell County and its neighbors

Counties shaded by data center MW on record, planned to operating. 5 of its 5 neighboring counties have pages of their own. The rest are in the member database.

Shackelford 1.8 GW Stonewall no data centers Knox no data centers Jones 0 MW Throckmorton no data centers Haskell 630 MW
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
36%

of the generation operating in the county is matched by data center MW on record: 630 MW of data centers against 1.8 GW of plants, with 6.3 GW more planned.

Data centers, planned to operating630 MW
Operating generation1.8 GW
Planned generation6.3 GW

Data centers by status

9 records, 630 MW

Under construction280 MW4 records, 44%
Planned350 MW5 records, 56%
Who owns each of the 9 records?Campus names, developers and contacts are for members.See what members get

The data center pipeline

9 records list a year online or expected, from 2027 to 2029. The largest expected additions are 280 MW listed for 2028 and 280 MW for 2029.

Figure 1

Data center MW by year online or expected

Records not cancelled, by listed year. 2026 onward is planned or under construction.

Through 20252026 and later
0100200300 70 2027 280 2028 280 2029
View as table
YearRecordsMW
2027170
20284280
20294280
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026. 9 records with a year
Figure 2

Who is building in Haskell

Data center developers by MW on record. Top 1 of 1.

Google 630 MW 9 sites
View as table
DeveloperSitesMW
Google9630
Members see all 1 developer, each campus they own here, and the people who run their site selection and energy procurement.
Aggregates only. Campus names are for members.

Power generation in the county

10 plants operate inside Haskell County, 1.8 GW. The queue adds 6.3 GW across 25 projects.

Figure 3

Operating and planned generation by technology

MW in Haskell County

OperatingPlanned
SolarOperating 705 MW 4 projects
SolarPlanned 3.5 GW 14 projects
Battery StorageOperating 104.2 MW 2 projects
Battery StoragePlanned 2 GW 8 projects
WindOperating 965 MW 4 projects
WindPlanned 800.8 MW 3 projects
View as table
TechnologyStatusProjectsMW
SolarOperating4705
SolarPlanned143,463.9
Battery StorageOperating2104.2
Battery StoragePlanned82,014.8
WindOperating4965
WindPlanned3800.8
Operating: 1.8 GW. Planned: 6.3 GW. Even if every planned project is built, county generation would reach 8.1 GW against 630 MW of data centers.
Source: ISO queues and EIA-860M, via FieldProspects
Figure 4

Planned generation by listed in-service year

MW. Years before 2026 are past due.

Past dueDue 2026 or later
01k2k3k4k Snapshot year 3,348 2026 723 2027 1,614 2028 595 2029
View as table
YearPlanned projectsMW
2026113,347.8
20274722.8
202871,613.9
20293595
No planned project is past its listed year

Haskell County against its neighbors

Shackelford County has the most data center MW among the neighbors, 1.8 GW, more than Haskell County. 3 of the 5 have more generation operating than data center MW on record.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
Shackelford County 10
1,820
566
410 3.2x
Haskell County this page 9
630
1,774
6,280 0.36x
Knox County 0
0
954
2,311 0x
Throckmorton County 0
0
679
745 0x
Jones County 2
0
201
5,199 0x
Stonewall County 0
0
0
1,594 no operating MW

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

6 counties shown

What changed since June 4, 2026

10 projects in Haskell County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.

Open the change feed
0
added to a queue, 0 MW
2
came online, started construction or signed an interconnection agreement, 358 MW
0
cancelled, dropped or went inactive, 0 MW
8
slipped their in-service date, 2.9 GW

Every change in Haskell County

Project, what changed, technology, MW and the dates that moved, for all 10 changes.

Members only
County: Haskell County, TXSince June 4, 2026 10 changes
ProjectChangeTechnologyMWPrevious dateNew date
10 changes behind this preview

Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.

Request access

Every record in Haskell County

Campus or project name, developer, status, MW, year and the developer’s contacts, for all 44 records. Filter, sort and export to Excel.

Members only
County: Haskell County, TXStatus: all except cancelledSort: MW, largest first 44 records
Project or campusDeveloperStatusMWYearContacts
44 records and 8.7 GW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Haskell County

We email you when a data center or power project in Haskell County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Haskell County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.