FieldProspects

Ector County, Texas

Ector County, Texas has 457 MW of data centers on record, planned to operating, across 2 records, against 2.9 GW of generation operating inside the county. The queue adds 4.6 GW of planned generation across 27 projects, 1 of them past its listed in-service date.

Data as of Grid region: ERCOTRefreshed monthly
457MW
data centers, planned to operating
2
data center records, not cancelled
0.4%
of Texas's data center MW
2.9GW
operating generation, 75 projects
4.6GW
planned generation, 27 projects
2
data center developers active here
Map

Ector County and its neighbors

Counties shaded by data center MW on record, planned to operating. 6 of its 6 neighboring counties have pages of their own. The rest are in the member database.

Upton 280 MW Midland 150 MW Andrews 100 MW Winkler 300 MW Crane no data centers Ward 234 MW Ector 457 MW
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
16%

of the generation operating in the county is matched by data center MW on record: 457 MW of data centers against 2.9 GW of plants, with 4.6 GW more planned.

Data centers, planned to operating457 MW
Operating generation2.9 GW
Planned generation4.6 GW

Data centers by status

2 records, 457 MW

Operating207 MW1 record, 45%
Planned250 MW1 record, 55%
Who owns each of the 2 records?Campus names, developers and contacts are for members.See what members get

The data center pipeline

1 record list a year online or expected, from 2022 to 2022. No record lists a year at or after the snapshot. 1 record list no year.

Figure 1

Data center MW by year online or expected

Records not cancelled, by listed year. 2026 onward is planned or under construction.

Through 20252026 and later
0100200300 207 2022
View as table
YearRecordsMW
20221207
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026. 1 record with a year; 1 without are left out
Figure 2

Who is building in Ector

Data center developers by MW on record. Top 2 of 2.

Texas Critical Data Centers 250 MW 1 site
Cipher Digital (formerly Cipher Mining) 207 MW 1 site
View as table
DeveloperSitesMW
Texas Critical Data Centers1250
Cipher Digital (formerly Cipher Mining)1207
Members see all 2 developers, each campus they own here, and the people who run their site selection and energy procurement.
Aggregates only. Campus names are for members.

Power generation in the county

75 plants operate inside Ector County, 2.9 GW. The queue adds 4.6 GW across 27 projects, and one of them is past its listed in-service date.

Figure 3

Operating and planned generation by technology

MW in Ector County

OperatingPlanned
SolarOperating 615.4 MW 6 projects
SolarPlanned 3 GW 15 projects
Natural GasOperating 2.1 GW 17 projects
Natural GasPlanned 122.8 MW 1 project
Battery StorageOperating 75.7 MW 5 projects
Battery StoragePlanned 1.5 GW 11 projects
WindOperating 152.5 MW 2 projects
OilOperating 27 MW 45 projects
View as table
TechnologyStatusProjectsMW
SolarOperating6615.4
SolarPlanned152,958.5
Natural GasOperating172,063.2
Natural GasPlanned1122.8
Battery StorageOperating575.7
Battery StoragePlanned111,541.7
WindOperating2152.5
OilOperating4527
Operating: 2.9 GW. Planned: 4.6 GW. Even if every planned project is built, county generation would reach 7.6 GW against 457 MW of data centers.
Source: ISO queues and EIA-860M, via FieldProspects
Figure 4

Planned generation by listed in-service year

MW. Years before 2026 are past due.

Past dueDue 2026 or later
05001k1.5k2k Snapshot year 102 2025 689 2026 256 2027 1,180 2028 1,995 2029 401 2030
View as table
YearPlanned projectsMW
20251101.6
20266689.3
20271256
202891,179.8
202991,995.1
20301401.3
1 project, 101.6 MW, was due before 2026

Ector County against its neighbors

Winkler County has the most data center MW among the neighbors, 300 MW, 66% of Ector County's. 4 of the 6 have more generation operating than data center MW on record.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
Ector County this page 2
457
2,934
4,623 0.16x
Winkler County 4
300
250
217 1.2x
Upton County 1
280
1,841
5,824 0.15x
Ward County 1
234
598
5,763 0.39x
Midland County 2
150
140
876 1.1x
Andrews County 1
100
1,298
2,784 0.08x
Crane County 0
0
503
3,144 0x

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

7 counties shown

What changed since June 4, 2026

10 projects in Ector County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.

Open the change feed
2
added to a queue, 602.8 MW
1
came online, started construction or signed an interconnection agreement, 150.7 MW
1
cancelled, dropped or went inactive, 206 MW
6
slipped their in-service date, 547.1 MW

Every change in Ector County

Project, what changed, technology, MW and the dates that moved, for all 10 changes.

Members only
County: Ector County, TXSince June 4, 2026 10 changes
ProjectChangeTechnologyMWPrevious dateNew date
10 changes behind this preview

Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.

Request access

Every record in Ector County

Campus or project name, developer, status, MW, year and the developer’s contacts, for all 104 records. Filter, sort and export to Excel.

Members only
County: Ector County, TXStatus: all except cancelledSort: MW, largest first 104 records
Project or campusDeveloperStatusMWYearContacts
104 records and 8 GW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Ector County

We email you when a data center or power project in Ector County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Ector County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.