Dickens County, Texas

Dickens County, Texas has 800 MW of data centers on record, planned to operating, across 4 records, against 450 MW of generation operating inside the county. The queue adds 2.5 GW of planned generation across 10 projects. That is 0.8% of Texas's data center MW.

Data as of Grid region: ERCOTRefreshed monthly
800MW
data centers, planned to operating
4
data center records, not cancelled
0.8%
of Texas's data center MW
450MW
operating generation, 3 projects
2.5GW
planned generation, 10 projects
1
data center developers active here
Map

Dickens County and its neighbors

Counties shaded by data center MW on record, planned to operating. 4 of its 4 neighboring counties have pages of their own. The rest are in the member database.

Dickens 800 MW King no data centers Motley no data centers Crosby no data centers Kent no data centers
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
1.8times

more data center MW than operating generation in the county. Dickens County's own plants cover 56.3% of the load on record, and the planned pipeline adds 2.5 GW.

Data centers, planned to operating800 MW
Operating generation450 MW
Planned generation2.5 GW

Data centers by status

4 records, 800 MW

Operating200 MW1 record, 25%
Planned600 MW3 records, 75%
Who owns each of the 4 records?Campus names, developers and contacts are for members.See what members get

The data center pipeline

4 records list a year online or expected, from 2026 to 2028. The largest expected additions are 400 MW listed for 2027 and 200 MW for 2026.

Figure 1

Data center MW by year online or expected

Records not cancelled, by listed year. 2026 onward is planned or under construction.

Through 20252026 and later
0100200300400 Snapshot year 200 2026 400 2027 200 2028
View as table
YearRecordsMW
20261200
20272400
20281200
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026. 4 records with a year
Figure 2

Who is building in Dickens

Data center developers by MW on record. Top 1 of 1.

Galaxy Digital 800 MW 4 sites
View as table
DeveloperSitesMW
Galaxy Digital4800
Members see all 1 developer, each campus they own here, and the people who run their site selection and energy procurement.
Aggregates only. Campus names are for members.

Power generation in the county

3 plants operate inside Dickens County, 450 MW of battery storage and wind. The queue adds 2.5 GW across 10 projects.

Figure 3

Operating and planned generation by technology

MW in Dickens County

OperatingPlanned
SolarPlanned 1.3 GW 6 projects
Battery StorageOperating 300 MW 2 projects
Battery StoragePlanned 922.5 MW 3 projects
WindOperating 150 MW 1 project
WindPlanned 292.6 MW 1 project
View as table
TechnologyStatusProjectsMW
SolarPlanned61,306
Battery StorageOperating2300
Battery StoragePlanned3922.5
WindOperating1150
WindPlanned1292.6
Operating: 450 MW. Planned: 2.5 GW. Even if every planned project is built, county generation would reach 3 GW against 800 MW of data centers.
Source: ISO queues and EIA-860M, via FieldProspects
Figure 4

Planned generation by listed in-service year

MW. Years before 2026 are past due.

Past dueDue 2026 or later
05001k1.5k2k 418 2027 1,509 2028 595 2029
View as table
YearPlanned projectsMW
20271417.8
202871,508.7
20292594.6
No planned project is past its listed year

Dickens County against its neighbors

None of the 4 neighboring counties with a page lists a data center record. Kent County has the most operating generation among them, 482 MW.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
Dickens County this page 4
800
450
2,521 1.8x
Kent County 0
0
482
1,395 0x
Crosby County 0
0
367
753 0x
Motley County 0
0
250
852 0x
King County 0
0
0
1,312 no operating MW

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

5 counties shown

What changed since June 4, 2026

8 projects in Dickens County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.

Open the change feed
0
added to a queue, 0 MW
4
came online, started construction or signed an interconnection agreement, 1.1 GW
0
cancelled, dropped or went inactive, 0 MW
4
slipped their in-service date, 996.9 MW

Every change in Dickens County

Project, what changed, technology, MW and the dates that moved, for all 8 changes.

Members only
County: Dickens County, TXSince June 4, 2026 8 changes
ProjectChangeTechnologyMWPrevious dateNew date
8 changes behind this preview

Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.

Request access

Every record in Dickens County

Campus or project name, developer, status, MW, year and the developer’s contacts, for all 17 records. Filter, sort and export to Excel.

Members only
County: Dickens County, TXStatus: all except cancelledSort: MW, largest first 17 records
Project or campusDeveloperStatusMWYearContacts
17 records and 3.8 GW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Dickens County

We email you when a data center or power project in Dickens County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Dickens County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.