Cameron County, Texas
Cameron County, Texas has 2.3 GW of data centers on record, planned to operating, across 4 records, against 1.6 GW of generation operating inside the county. The queue adds 7.3 GW of planned generation across 37 projects. That is 2.2% of Texas's data center MW.
Cameron County and its neighbors
Counties shaded by data center MW on record, planned to operating. 2 of its 2 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
more data center MW than operating generation in the county. Cameron County's own plants cover 67.8% of the load on record, and the planned pipeline adds 7.3 GW.
Data centers by status
4 records, 2.3 GW
The data center pipeline
1 record list a year online or expected, from 2028 to 2028. The largest expected additions are 0 MW listed for 2028. 3 records list no year.
Data center MW by year online or expected
Records not cancelled, by listed year. 2026 onward is planned or under construction.
View as table
| Year | Records | MW |
|---|---|---|
| 2028 | 1 | 0 |
Who is building in Cameron
Data center developers by MW on record. Top 3 of 3.
View as table
| Developer | Sites | MW |
|---|---|---|
| Eneus Energy | 1 | 2,000 |
| Soluna Holdings | 2 | 287 |
| Fluidstack | 1 | 0 |
Power generation in the county
88 plants operate inside Cameron County, 1.6 GW. The queue adds 7.3 GW across 37 projects.
Operating and planned generation by technology
MW in Cameron County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Battery Storage | Operating | 9 | 186.3 |
| Battery Storage | Planned | 27 | 4,101.8 |
| Natural Gas | Operating | 6 | 137.2 |
| Natural Gas | Planned | 1 | 1,536.4 |
| Solar | Operating | 2 | 180 |
| Solar | Planned | 7 | 1,288.6 |
| Wind | Operating | 6 | 1,005.3 |
| Wind | Planned | 1 | 300 |
| Hydrogen | Planned | 1 | 79.6 |
| Oil | Operating | 65 | 42.5 |
Planned generation by listed in-service year
MW. Years before 2026 are past due.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2026 | 9 | 921.8 |
| 2027 | 5 | 2,406.7 |
| 2028 | 16 | 2,531.5 |
| 2029 | 6 | 1,146.4 |
| 2030 | 1 | 300 |
Cameron County against its neighbors
Willacy County has the most data center MW among the neighbors, 286 MW, 13% of Cameron County's. 2 of the 2 have more generation operating than data center MW on record.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| Cameron County this page | 4 | 7,307 | 1.5x | ||
| Willacy County | 2 | 787 | 0.2x | ||
| Hidalgo County | 0 | 4,909 | 0x |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
3 counties shownWhat changed since June 4, 2026
14 projects in Cameron County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.
Every change in Cameron County
Project, what changed, technology, MW and the dates that moved, for all 14 changes.
| Project | Change | Technology | MW | Previous date | New date |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.
Every record in Cameron County
Campus or project name, developer, status, MW, year and the developer’s contacts, for all 129 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for Cameron County
We email you when a data center or power project in Cameron County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.