Union County, Pennsylvania has 300 MW of data centers on record, planned to operating, across 4 records, against 12.7 MW of generation operating inside the county. The queue adds 200 MW of planned generation across 4 projects. That is 1.6% of Pennsylvania's data center MW.
Union County and its neighbors
Counties shaded by data center MW on record, planned to operating. 4 of its 6 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
more data center MW than operating generation in the county. Union County's own plants cover 4.2% of the load on record, and the planned pipeline adds 200 MW.
Data centers by status
4 records, 300 MW
The data center pipeline
4 records list a year online or expected, from 2027 to 2029. The largest expected additions are 180 MW listed for 2028 and 80 MW for 2029.
Data center MW by year online or expected
Records not cancelled, by listed year. 2026 onward is planned or under construction.
View as table
| Year | Records | MW |
|---|---|---|
| 2027 | 1 | 40 |
| 2028 | 2 | 180 |
| 2029 | 1 | 80 |
Who is building in Union
Data center developers by MW on record. Top 1 of 1.
View as table
| Developer | Sites | MW |
|---|---|---|
| PNK Group | 4 | 300 |
Power generation in the county
5 plants operate inside Union County, 12.7 MW. The queue adds 200 MW across 4 projects.
Operating and planned generation by technology
MW in Union County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Solar | Operating | 1 | 1.4 |
| Solar | Planned | 4 | 200 |
| Natural Gas | Operating | 2 | 5.9 |
| Oil | Operating | 2 | 5.4 |
Planned generation by listed in-service year
MW. Years before 2026 are past due.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2027 | 4 | 200 |
Union County against its neighbors
None of the 4 neighboring counties with a page lists a data center record. Snyder County has the most operating generation among them, 1.3 GW.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| Union County this page | 4 | 200 | 23.6x | ||
| Snyder County | 0 | 1,268 | 0x | ||
| Lycoming County | 0 | 910 | 0x | ||
| Northumberland County | 0 | 155 | 0x | ||
| Centre County | 0 | 853 | 0x |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
5 counties shownWhat changed since June 4, 2026
5 projects in Union County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.
Every change in Union County
Project, what changed, technology, MW and the dates that moved, for all 5 changes.
| Project | Change | Technology | MW | Previous date | New date |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.
Every record in Union County
Campus or project name, developer, status, MW, year and the developer’s contacts, for all 13 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for Union County
We email you when a data center or power project in Union County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.
Open every campus, project and contact in Union County.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.