Muskogee County, Oklahoma
Muskogee County, Oklahoma has 1.4 GW of data centers on record, planned to operating, across 11 records, against 1.9 GW of generation operating inside the county. The queue adds 1.5 GW of planned generation across 6 projects. That is 21.4% of Oklahoma's data center MW.
Muskogee County and its neighbors
Counties shaded by data center MW on record, planned to operating. 4 of its 6 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
of the generation operating in the county is matched by data center MW on record: 1.4 GW of data centers against 1.9 GW of plants, with 1.5 GW more planned.
Data centers by status
11 records, 1.4 GW
The data center pipeline
9 records list a year online or expected, from 2026 to 2034. The largest expected additions are 234 MW listed for 2028 and 198.5 MW for 2027. 2 records list no year.
Data center MW by year online or expected
Records not cancelled, by listed year. 2026 onward is planned or under construction.
View as table
| Year | Records | MW |
|---|---|---|
| 2026 | 1 | 100 |
| 2027 | 2 | 199 |
| 2028 | 2 | 234 |
| 2029 | 1 | 102 |
| 2030 | 1 | 118 |
| 2031 | 0 | 0 |
| 2032 | 1 | 118 |
| 2033 | 0 | 0 |
| 2034 | 1 | 118 |
Who is building in Muskogee
Data center developers by MW on record. Top 3 of 3.
View as table
| Developer | Sites | MW |
|---|---|---|
| 7 | 806 | |
| Core Scientific | 3 | 623 |
| CoreWeave | 1 | 0 |
Power generation in the county
9 plants operate inside Muskogee County, 1.9 GW. The queue adds 1.5 GW across 6 projects.
Operating and planned generation by technology
MW in Muskogee County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Solar | Planned | 4 | 1,290 |
| Natural Gas | Operating | 5 | 1,258 |
| Coal | Operating | 1 | 572 |
| Battery Storage | Planned | 2 | 175 |
| Hydro | Operating | 3 | 75 |
Planned generation by listed in-service year
MW. Years before 2026 are past due.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2026 | 1 | 200 |
| 2027 | 1 | 400 |
| 2028 | 1 | 100 |
| 2029 | 0 | 0 |
| 2030 | 1 | 390 |
| 2031 | 2 | 375 |
Muskogee County against its neighbors
Wagoner County has the most data center MW among the neighbors, 494 MW, 35% of Muskogee County's. 4 of the 4 have more generation operating than data center MW on record.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| Muskogee County this page | 11 | 1,465 | 0.75x | ||
| Wagoner County | 5 | 601 | 0.41x | ||
| Sequoyah County | 0 | 170 | 0x | ||
| Haskell County | 0 | 0 | 0x | ||
| Cherokee County | 0 | 0 | 0x |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
5 counties shownEvery record in Muskogee County
Campus or project name, developer, status, MW, year and the developer’s contacts, for all 26 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for Muskogee County
We email you when a data center or power project in Muskogee County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.