Shelby County, Ohio

Shelby County, Ohio has 300 MW of data centers on record, planned to operating, across 4 records, against 16.9 MW of generation operating inside the county. Nothing is in the interconnection queue for the county. That is 1% of Ohio's data center MW.

Data as of Grid region: PJM InterconnectionRefreshed monthly
300MW
data centers, planned to operating
4
data center records, not cancelled
1%
of Ohio's data center MW
16.9MW
operating generation, 7 projects
0MW
planned generation, 0 projects
1
data center developers active here
Map

Shelby County and its neighbors

Counties shaded by data center MW on record, planned to operating. 5 of its 6 neighboring counties have pages of their own. The rest are in the member database.

Shelby 300 MW Darke no data centers Logan no data centers Auglaize no data centers Miami 1.4 GW Champaign 0 MW Mercer
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
17.8times

more data center MW than operating generation in the county. Shelby County's own plants cover 5.6% of the load on record, and nothing is in the queue.

Data centers, planned to operating300 MW
Operating generation16.9 MW
Planned generation0 MW

Data centers by status

4 records, 300 MW

Planned300 MW4 records, 100%
Who owns each of the 4 records?Campus names, developers and contacts are for members.See what members get

The data center pipeline

4 records list a year online or expected, from 2028 to 2028. The largest expected additions are 300 MW listed for 2028.

Figure 1

Data center MW by year online or expected

Records not cancelled, by listed year. 2026 onward is planned or under construction.

Through 20252026 and later
0100200300 300 2028
View as table
YearRecordsMW
20284300
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026. 4 records with a year
Figure 2

Who is building in Shelby

Data center developers by MW on record. Top 1 of 1.

Amazon 300 MW 4 sites
View as table
DeveloperSitesMW
Amazon4300
Members see all 1 developer, each campus they own here, and the people who run their site selection and energy procurement.
Aggregates only. Campus names are for members.

Power generation in the county

7 plants operate inside Shelby County, 16.9 MW of oil and solar. Nothing is in the queue for the county.

Figure 3

Operating and planned generation by technology

MW in Shelby County

OperatingPlanned
OilOperating 15.3 MW 6 projects
SolarOperating 1.6 MW 1 project
View as table
TechnologyStatusProjectsMW
OilOperating615.3
SolarOperating11.6
Operating: 16.9 MW. Planned: 0 MW. Even if every planned project is built, county generation would reach 16.9 MW against 300 MW of data centers.
Source: ISO queues and EIA-860M, via FieldProspects

Shelby County against its neighbors

Miami County has the most data center MW among the neighbors, 1.4 GW, more than Shelby County. 4 of the 5 have more generation operating than data center MW on record.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
Miami County 4
1,400
51
0 27.6x
Shelby County this page 4
300
17
0 17.8x
Logan County 0
0
253
413 0x
Darke County 0
0
248
0 0x
Champaign County 1
0
144
288 0x
Auglaize County 0
0
50
0 0x

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

6 counties shown

Every record in Shelby County

Campus or project name, developer, status, MW, year and the developer’s contacts, for all 11 records. Filter, sort and export to Excel.

Members only
County: Shelby County, OHStatus: all except cancelledSort: MW, largest first 11 records
Project or campusDeveloperStatusMWYearContacts
11 records and 316.9 MW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Shelby County

We email you when a data center or power project in Shelby County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Shelby County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.