Warren County, Missouri

Warren County, Missouri has 600 MW of data centers on record, planned to operating, across 2 records, against 439 MW of generation operating inside the county. The queue adds 639 MW of planned generation across 3 projects, 2 of them past their listed in-service date.

Data as of Grid region: Midcontinent ISO (MISO)Refreshed monthly
600MW
data centers, planned to operating
2
data center records, not cancelled
8.4%
of Missouri's data center MW
439MW
operating generation, 2 solar projects
639MW
planned generation, 3 projects
1
data center developers active here
Map

Warren County and its neighbors

Counties shaded by data center MW on record, planned to operating. 3 of its 5 neighboring counties have pages of their own. The rest are in the member database.

Warren 600 MW Franklin no data centers Montgomery 2.5 GW Lincoln St Charles no data centers Gasconade
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
1.4times

more data center MW than operating generation in the county. Warren County's own plants cover 73.2% of the load on record, and the planned pipeline adds 639 MW.

Data centers, planned to operating600 MW
Operating generation439 MW
Planned generation639 MW

Data centers by status

2 records, 600 MW

Planned600 MW2 records, 100%
Who owns each of the 2 records?Campus names, developers and contacts are for members.See what members get

The data center pipeline

2 records list a year online or expected, from 2028 to 2029. The largest expected additions are 300 MW listed for 2028 and 300 MW for 2029.

Figure 1

Data center MW by year online or expected

Records not cancelled, by listed year. 2026 onward is planned or under construction.

Through 20252026 and later
0100200300 300 2028 300 2029
View as table
YearRecordsMW
20281300
20291300
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026. 2 records with a year
Figure 2

Who is building in Warren

Data center developers by MW on record. Top 1 of 1.

Crusoe 600 MW 2 sites
View as table
DeveloperSitesMW
Crusoe2600
Members see all 1 developer, each campus they own here, and the people who run their site selection and energy procurement.
Aggregates only. Campus names are for members.

Power generation in the county

2 plants operate inside Warren County, 439 MW of solar. The queue adds 639 MW across 3 projects, and 2 of them are past their listed in-service date.

Figure 3

Operating and planned generation by technology

MW in Warren County

OperatingPlanned
SolarOperating 439 MW 2 projects
SolarPlanned 639 MW 3 projects
View as table
TechnologyStatusProjectsMW
SolarOperating2439
SolarPlanned3639
Operating: 439 MW. Planned: 639 MW. Even if every planned project is built, county generation would reach 1.1 GW against 600 MW of data centers.
Source: ISO queues and EIA-860M, via FieldProspects
Figure 4

Planned generation by listed in-service year

MW. Years before 2026 are past due.

Past dueDue 2026 or later
0100200300 Snapshot year 139 2021 2022 2023 300 2024 2025 200 2026
View as table
YearPlanned projectsMW
20211139
202200
202300
20241300
202500
20261200
2 projects, 439 MW, were due before 2026

Warren County against its neighbors

Montgomery County has the most data center MW among the neighbors, 2.5 GW, more than Warren County. 2 of the 3 have more generation operating than data center MW on record.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
Montgomery County 19
2,475
6
200 434x
Warren County this page 2
600
439
639 1.4x
Franklin County 0
0
2,389
0 0x
St Charles County 0
0
1,104
2,220 0x

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

4 counties shown

What changed since June 4, 2026

1 project in Warren County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.

Open the change feed
0
added to a queue, 0 MW
1
came online, started construction or signed an interconnection agreement, 300 MW
0
cancelled, dropped or went inactive, 0 MW
0
slipped their in-service date, 0 MW

Every change in Warren County

Project, what changed, technology, MW and the dates that moved, for all 1 change.

Members only
County: Warren County, MOSince June 4, 2026 1 change
ProjectChangeTechnologyMWPrevious dateNew date
1 change behind this preview

Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.

Request access

Every record in Warren County

Campus or project name, developer, status, MW, year and the developer’s contacts, for all 7 records. Filter, sort and export to Excel.

Members only
County: Warren County, MOStatus: all except cancelledSort: MW, largest first 7 records
Project or campusDeveloperStatusMWYearContacts
7 records and 1.7 GW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Warren County

We email you when a data center or power project in Warren County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Warren County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.