Palo Alto County, Iowa

Palo Alto County, Iowa has 13 power projects in the FieldProspects database: 10 operating plants totaling 374.3 MW and 3 planned projects totaling 650 MW. No data center record lists the county. Wind leads with 761 MW across 5 projects.

Data as of Grid region: Midcontinent ISO (MISO)Refreshed monthly
13
power projects, planned and operating
650MW
planned generation, 3 projects
374.3MW
operating generation, 10 projects
2
planned projects past their listed in-service date
Map

Palo Alto County and its neighbors

Counties shaded by data center MW on record, planned to operating. 4 of its 4 neighboring counties have pages of their own. The rest are in the member database.

Emmet no data centers Pocahontas no data centers Clay no data centers Kossuth no data centers Palo Alto no data centers
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
1.7times

more planned than operating generation in Palo Alto County. 3 projects in the queue would add 650 MW to the 374.3 MW operating today, and 2 of them are past their listed in-service date.

Operating generation374.3 MW
Planned generation650 MW

Technology mix

13 projects, 1 GW planned and operating

Wind761 MW5 projects, 74%
Solar250 MW1 project, 24%
Oil9.8 MW6 projects, 1%
One other technology3.5 MW1 project, 0%
Which companies own these 13 projects?Project names, developers and contacts are for members.See what members get

Power generation in the county

10 plants operate inside Palo Alto County, 374.3 MW. The queue adds 650 MW across 3 projects, and 2 of them are past their listed in-service date.

Figure 1

Operating and planned generation by technology

MW in Palo Alto County

OperatingPlanned
WindOperating 361 MW 3 projects
WindPlanned 400 MW 2 projects
SolarPlanned 250 MW 1 project
OilOperating 9.8 MW 6 projects
Natural GasOperating 3.5 MW 1 project
View as table
TechnologyStatusProjectsMW
WindOperating3361
WindPlanned2400
SolarPlanned1250
OilOperating69.8
Natural GasOperating13.5
Operating: 374.3 MW. Planned: 650 MW. If every planned project is built, county generation would reach 1 GW.
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026.
Figure 2

Planned generation by listed in-service year

MW. Years before 2026 are past due.

Past dueDue 2026 or later
0100200300 Snapshot year 250 2023 200 2024 2025 2026 2027 2028 200 2029
View as table
YearPlanned projectsMW
20231250
20241200
202500
202600
202700
202800
20291200
2 projects, 450 MW, were due before 2026

Palo Alto County against its neighbors

None of the 4 neighboring counties with a page lists a data center record. Kossuth County has the most operating generation among them, 462.3 MW.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
Kossuth County 0
0
462
275 0x
Clay County 0
0
442
0 0x
Pocahontas County 0
0
378
156 0x
Palo Alto County this page 0
0
374
650 0x
Emmet County 0
0
17
0 0x

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

5 counties shown

Every record in Palo Alto County

Project name, developer, status, MW, in-service year and the developer’s contacts, for all 13 records. Filter, sort and export to Excel.

Members only
County: Palo Alto County, IAStatus: all except cancelledSort: MW, largest first 13 records
Project or campusDeveloperStatusMWYearContacts
13 records and 1 GW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Palo Alto County

We email you when a data center or power project in Palo Alto County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Palo Alto County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.