Linn County, Iowa

Linn County, Iowa has 2.8 GW of data centers on record, planned to operating, across 19 records, against 742.3 MW of generation operating inside the county. The queue adds 2.5 GW of planned generation across 12 projects, 5 of them past their listed in-service date.

Data as of Grid region: Midcontinent ISO (MISO)Refreshed monthly
2.8GW
data centers, planned to operating
19
data center records, not cancelled
36.8%
of Iowa's data center MW
742.3MW
operating generation, 38 projects
2.5GW
planned generation, 12 projects
2
data center developers active here
Map

Linn County and its neighbors

Counties shaded by data center MW on record, planned to operating. 4 of its 6 neighboring counties have pages of their own. The rest are in the member database.

Cedar no data centers Delaware no data centers Buchanan Jones Linn 2.8 GW Johnson no data centers Benton no data centers
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
3.8times

more data center MW than operating generation in the county. Linn County's own plants cover 26.6% of the load on record, and the planned pipeline adds 2.5 GW.

Data centers, planned to operating2.8 GW
Operating generation742.3 MW
Planned generation2.5 GW

Data centers by status

19 records, 2.8 GW

Under construction1.9 GW10 records, 67%
Planned909.9 MW9 records, 33%
Who owns each of the 19 records?Campus names, developers and contacts are for members.See what members get

The data center pipeline

19 records list a year online or expected, from 2026 to 2030. The largest expected additions are 1.2 GW listed for 2027 and 724.5 MW for 2026.

Figure 1

Data center MW by year online or expected

Records not cancelled, by listed year. 2026 onward is planned or under construction.

Through 20252026 and later
05001k1.5k Snapshot year 725 2026 1,160 2027 2028 507 2029 2030
View as table
YearRecordsMW
20264725
202761,160
202800
20295507
20304403
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026. 19 records with a year
Figure 2

Who is building in Linn

Data center developers by MW on record. Top 2 of 2.

QTS 1.6 GW 7 sites
Google 1.2 GW 12 sites
View as table
DeveloperSitesMW
QTS71,587
Google121,208
Members see all 2 developers, each campus they own here, and the people who run their site selection and energy procurement.
Aggregates only. Campus names are for members.

Power generation in the county

38 plants operate inside Linn County, 742.3 MW. The queue adds 2.5 GW across 12 projects, and 5 of them are past their listed in-service date.

Figure 3

Operating and planned generation by technology

MW in Linn County

OperatingPlanned
SolarOperating 204.5 MW 3 projects
SolarPlanned 760 MW 4 projects
NuclearPlanned 646 MW 1 project
TransmissionPlanned 615 MW 4 projects
Battery StorageOperating 5 MW 1 project
Battery StoragePlanned 400 MW 2 projects
CoalOperating 306.1 MW 7 projects
Natural GasOperating 187.3 MW 2 projects
Natural GasPlanned 95 MW 1 project
OilOperating 39.4 MW 25 projects
View as table
TechnologyStatusProjectsMW
SolarOperating3204.5
SolarPlanned4760
NuclearPlanned1646
TransmissionPlanned4615
Battery StorageOperating15
Battery StoragePlanned2400
CoalOperating7306.1
Natural GasOperating2187.3
Natural GasPlanned195
OilOperating2539.4
Operating: 742.3 MW. Planned: 2.5 GW. Even if every planned project is built, county generation would reach 3.3 GW against 2.8 GW of data centers.
Source: ISO queues and EIA-860M, via FieldProspects
Figure 4

Planned generation by listed in-service year

MW. Years before 2026 are past due.

Past dueDue 2026 or later
0200400600800 Snapshot year 400 2024 455 2025 2026 400 2027 615 2028 646 2029
View as table
YearPlanned projectsMW
20241400
20254455
202600
20272400
20284615
20291646
5 projects, 855 MW, were due before 2026

Linn County against its neighbors

None of the 4 neighboring counties with a page lists a data center record. Johnson County has the most operating generation among them, 124.3 MW.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
Linn County this page 19
2,795
742
2,516 3.8x
Johnson County 0
0
124
153 0x
Delaware County 0
0
110
0 0x
Benton County 0
0
18
0 0x
Cedar County 0
0
14
9 0x

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

5 counties shown

What changed since June 4, 2026

1 project in Linn County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.

Open the change feed
0
added to a queue, 0 MW
0
came online, started construction or signed an interconnection agreement, 0 MW
1
cancelled, dropped or went inactive, 195 MW
0
slipped their in-service date, 0 MW

Every change in Linn County

Project, what changed, technology, MW and the dates that moved, for all 1 change.

Members only
County: Linn County, IASince June 4, 2026 1 change
ProjectChangeTechnologyMWPrevious dateNew date
1 change behind this preview

Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.

Request access

Every record in Linn County

Campus or project name, developer, status, MW, year and the developer’s contacts, for all 69 records. Filter, sort and export to Excel.

Members only
County: Linn County, IAStatus: all except cancelledSort: MW, largest first 69 records
Project or campusDeveloperStatusMWYearContacts
69 records and 6.1 GW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Linn County

We email you when a data center or power project in Linn County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Linn County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.