White County, Indiana
White County, Indiana has 0 MW of data centers on record, planned to operating, across 1 record, against 1.8 GW of generation operating inside the county. The queue adds 3.7 GW of planned generation across 25 projects, 7 of them past their listed in-service date.
White County and its neighbors
Counties shaded by data center MW on record, planned to operating. 6 of its 6 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
of the generation operating in the county is matched by data center MW on record: 0 MW of data centers against 1.8 GW of plants, with 3.7 GW more planned.
Data centers by status
1 record, 0 MW
Power generation in the county
34 plants operate inside White County, 1.8 GW. The queue adds 3.7 GW across 25 projects, and 7 of them are past their listed in-service date.
Operating and planned generation by technology
MW in White County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Solar | Operating | 3 | 550 |
| Solar | Planned | 11 | 1,820 |
| Wind | Operating | 8 | 1,217.2 |
| Wind | Planned | 2 | 400.2 |
| Battery Storage | Operating | 1 | 45 |
| Battery Storage | Planned | 10 | 1,258 |
| Solar + Storage (Hybrid) | Planned | 1 | 200 |
| Transmission | Planned | 1 | 60 |
| Hydro | Operating | 4 | 7.3 |
| Landfill Gas | Operating | 4 | 6.4 |
| Natural Gas | Operating | 8 | 6.4 |
| Biomass | Operating | 6 | 6 |
Planned generation by listed in-service year
MW. Years before 2026 are past due. 4 planned projects list no date and are left out.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2021 | 2 | 400.2 |
| 2022 | 1 | 200 |
| 2023 | 1 | 50 |
| 2024 | 3 | 300 |
| 2025 | 0 | 0 |
| 2026 | 5 | 1,110 |
| 2027 | 7 | 1,118 |
| 2028 | 2 | 300 |
White County against its neighbors
Jasper County has the most data center MW among the neighbors, 675 MW, more than White County. 6 of the 6 have more generation operating than data center MW on record.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| Jasper County | 9 | 2,535 | 0.41x | ||
| White County this page | 1 | 3,738 | 0x | ||
| Benton County | 0 | 430 | 0x | ||
| Cass County | 0 | 200 | 0x | ||
| Tippecanoe County | 0 | 100 | 0x | ||
| Carroll County | 0 | 0 | 0x | ||
| Pulaski County | 0 | 5,205 | 0x |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
7 counties shownWhat changed since June 4, 2026
13 projects in White County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.
Every change in White County
Project, what changed, technology, MW and the dates that moved, for all 13 changes.
| Project | Change | Technology | MW | Previous date | New date |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.
Every record in White County
Campus or project name, developer, status, MW, year and the developer’s contacts, for all 60 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for White County
We email you when a data center or power project in White County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.
Open every campus, project and contact in White County.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.