Starke County, Indiana

Starke County, Indiana has 8 power projects in the FieldProspects database: 3 operating plants totaling 891.3 MW and 5 planned projects totaling 900 MW. No data center record lists the county. Solar leads with 1.7 GW across 7 projects. 2 planned projects are past their listed in-service date.

Data as of Grid region: Midcontinent ISO (MISO)Refreshed monthly
8
power projects, planned and operating
900MW
planned generation, 5 projects
891.3MW
operating generation, 3 projects
2
planned projects past their listed in-service date
Map

Starke County and its neighbors

Counties shaded by data center MW on record, planned to operating. 5 of its 5 neighboring counties have pages of their own. The rest are in the member database.

Starke no data centers Marshall no data centers Pulaski no data centers St Joseph 3.2 GW Jasper 675 MW LaPorte 1.8 GW
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
1times

more planned than operating generation in Starke County. 5 projects in the queue would add 900 MW to the 891.3 MW operating today, and 2 of them are past their listed in-service date.

Operating generation891.3 MW
Planned generation900 MW

Technology mix

8 projects, 1.8 GW planned and operating

Solar1.7 GW7 projects, 97%
Battery Storage56.3 MW1 project, 3%
Which companies own these 8 projects?Project names, developers and contacts are for members.See what members get

Power generation in the county

3 plants operate inside Starke County, 891.3 MW of solar and battery storage. The queue adds 900 MW across 5 projects, and 2 of them are past their listed in-service date.

Figure 1

Operating and planned generation by technology

MW in Starke County

OperatingPlanned
SolarOperating 835 MW 2 projects
SolarPlanned 900 MW 5 projects
Battery StorageOperating 56.3 MW 1 project
View as table
TechnologyStatusProjectsMW
SolarOperating2835
SolarPlanned5900
Battery StorageOperating156.3
Operating: 891.3 MW. Planned: 900 MW. If every planned project is built, county generation would reach 1.8 GW.
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026.
Figure 2

Planned generation by listed in-service year

MW. Years before 2026 are past due. 1 planned project lists no date and is left out.

Past dueDue 2026 or later
0100200300 Snapshot year 210 2023 100 2024 2025 180 2026 2027 2028 200 2029
View as table
YearPlanned projectsMW
20231210
20241100
202500
20261180
202700
202800
20291200
2 projects, 310 MW, were due before 2026

Starke County against its neighbors

St Joseph County has the most data center MW among the neighbors, 3.2 GW. 3 of the 5 have more generation operating than data center MW on record.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
St Joseph County 39
3,202
1,012
2,614 3.2x
LaPorte County 20
1,779
546
1,309 3.3x
Jasper County 9
675
1,637
2,535 0.41x
Starke County this page 0
0
891
900 0x
Marshall County 0
0
14
2,000 0x
Pulaski County 0
0
3
5,205 0x

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

6 counties shown

What changed since June 4, 2026

2 projects in Starke County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.

Open the change feed
0
added to a queue, 0 MW
0
came online, started construction or signed an interconnection agreement, 0 MW
2
cancelled, dropped or went inactive, 700 MW
0
slipped their in-service date, 0 MW

Every change in Starke County

Project, what changed, technology, MW and the dates that moved, for all 2 changes.

Members only
County: Starke County, INSince June 4, 2026 2 changes
ProjectChangeTechnologyMWPrevious dateNew date
2 changes behind this preview

Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.

Request access

Every record in Starke County

Project name, developer, status, MW, in-service year and the developer’s contacts, for all 8 records. Filter, sort and export to Excel.

Members only
County: Starke County, INStatus: all except cancelledSort: MW, largest first 8 records
Project or campusDeveloperStatusMWYearContacts
8 records and 1.8 GW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Starke County

We email you when a data center or power project in Starke County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Starke County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.