Lake County, Indiana

Lake County, Indiana has 2.9 GW of data centers on record, planned to operating, across 32 records, against 1.2 GW of generation operating inside the county. The queue adds 1.4 GW of planned generation across 8 projects, 4 of them past their listed in-service date.

Data as of Grid region: Midcontinent ISO (MISO)Refreshed monthly
2.9GW
data centers, planned to operating
32
data center records, not cancelled
17.3%
of Indiana's data center MW
1.2GW
operating generation, 19 projects
1.4GW
planned generation, 8 projects
7
data center developers active here
Map

Lake County and its neighbors

Counties shaded by data center MW on record, planned to operating. 3 of its 3 neighboring counties have pages of their own. The rest are in the member database.

Lake 2.9 GW Newton no data centers Porter 21.7 MW Jasper 675 MW
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
2.5times

more data center MW than operating generation in the county. Lake County's own plants cover 39.7% of the load on record, and the planned pipeline adds 1.4 GW.

Data centers, planned to operating2.9 GW
Operating generation1.2 GW
Planned generation1.4 GW

Data centers by status

32 records, 2.9 GW

Operating20 MW1 record, 1%
Planned2.9 GW31 records, 99%
Who owns each of the 32 records?Campus names, developers and contacts are for members.See what members get

The data center pipeline

28 records list a year online or expected, from 2020 to 2030. The largest expected additions are 750 MW listed for 2028 and 675 MW for 2030. 4 records list no year.

Figure 1

Data center MW by year online or expected

Records not cancelled, by listed year. 2026 onward is planned or under construction.

Through 20252026 and later
0200400600800 Snapshot year 2020 2021 2022 2023 2024 2025 2026 2027 750 2028 525 2029 675 2030
View as table
YearRecordsMW
2020120
202100
202200
202300
202400
202500
202600
20271450
202810750
20297525
20309675
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026. 28 records with a year; 4 without are left out
Figure 2

Who is building in Lake

Data center developers by MW on record. Top 6 of 7.

Amazon 2 GW 26 sites
Sentinel Data Centers 504 MW 1 site
PowerHouse 450 MW 1 site
Decennial Group 20 MW 1 site
Karis Critical 0 MW 1 site
Province Group 0 MW 1 site
View as table
DeveloperSitesMW
Amazon261,950
Sentinel Data Centers1504
PowerHouse1450
Decennial Group120
Karis Critical10
Province Group10
Members see all 7 developers, each campus they own here, and the people who run their site selection and energy procurement.
Aggregates only. Campus names are for members.

Power generation in the county

19 plants operate inside Lake County, 1.2 GW. The queue adds 1.4 GW across 8 projects, and 4 of them are past their listed in-service date.

Figure 3

Operating and planned generation by technology

MW in Lake County

OperatingPlanned
Natural GasOperating 1.1 GW 14 projects
SolarOperating 6.5 MW 4 projects
SolarPlanned 700 MW 4 projects
TransmissionPlanned 350 MW 3 projects
Battery StoragePlanned 300 MW 1 project
Waste HeatOperating 94.6 MW 1 project
View as table
TechnologyStatusProjectsMW
Natural GasOperating141,058.6
SolarOperating46.5
SolarPlanned4700
TransmissionPlanned3350
Battery StoragePlanned1300
Waste HeatOperating194.6
Operating: 1.2 GW. Planned: 1.4 GW. Even if every planned project is built, county generation would reach 2.5 GW against 2.9 GW of data centers.
Source: ISO queues and EIA-860M, via FieldProspects
Figure 4

Planned generation by listed in-service year

MW. Years before 2026 are past due.

Past dueDue 2026 or later
0200400600 Snapshot year 550 2024 100 2025 2026 300 2027 400 2028
View as table
YearPlanned projectsMW
20243550
20251100
202600
20271300
20283400
4 projects, 650 MW, were due before 2026

Lake County against its neighbors

Jasper County has the most data center MW among the neighbors, 675 MW, 23% of Lake County's. 2 of the 3 have more generation operating than data center MW on record.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
Lake County this page 32
2,924
1,160
1,350 2.5x
Jasper County 9
675
1,637
2,535 0.41x
Porter County 1
22
240
150 0.09x
Newton County 0
0
0
450 no operating MW

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

4 counties shown

What changed since June 4, 2026

3 projects in Lake County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.

Open the change feed
2
added to a queue, 150 MW
0
came online, started construction or signed an interconnection agreement, 0 MW
0
cancelled, dropped or went inactive, 0 MW
1
slipped its in-service date, 300 MW

Every change in Lake County

Project, what changed, technology, MW and the dates that moved, for all 3 changes.

Members only
County: Lake County, INSince June 4, 2026 3 changes
ProjectChangeTechnologyMWPrevious dateNew date
3 changes behind this preview

Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.

Request access

Every record in Lake County

Campus or project name, developer, status, MW, year and the developer’s contacts, for all 59 records. Filter, sort and export to Excel.

Members only
County: Lake County, INStatus: all except cancelledSort: MW, largest first 59 records
Project or campusDeveloperStatusMWYearContacts
59 records and 5.4 GW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Lake County

We email you when a data center or power project in Lake County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Lake County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.