Hendricks County, Indiana

Hendricks County, Indiana has 424 MW of data centers on record, planned to operating, across 4 records, against 22.8 MW of generation operating inside the county. Nothing is in the interconnection queue for the county. That is 2.5% of Indiana's data center MW.

Data as of Grid region: Midcontinent ISO (MISO)Refreshed monthly
424MW
data centers, planned to operating
4
data center records, not cancelled
2.5%
of Indiana's data center MW
22.8MW
operating generation, 18 projects
0MW
planned generation, 0 projects
2
data center developers active here
Map

Hendricks County and its neighbors

Counties shaded by data center MW on record, planned to operating. 3 of its 5 neighboring counties have pages of their own. The rest are in the member database.

Hendricks 424 MW Boone Marion 404.3 MW Montgomery no data centers Morgan 1.2 GW Putnam
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
18.6times

more data center MW than operating generation in the county. Hendricks County's own plants cover 5.4% of the load on record, and nothing is in the queue.

Data centers, planned to operating424 MW
Operating generation22.8 MW
Planned generation0 MW

Data centers by status

4 records, 424 MW

Planned424 MW4 records, 100%
Who owns each of the 4 records?Campus names, developers and contacts are for members.See what members get

The data center pipeline

3 records list a year online or expected, from 2028 to 2029. The largest expected additions are 256 MW listed for 2028 and 144 MW for 2029. 1 record list no year.

Figure 1

Data center MW by year online or expected

Records not cancelled, by listed year. 2026 onward is planned or under construction.

Through 20252026 and later
0100200300 256 2028 144 2029
View as table
YearRecordsMW
20281256
20292144
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026. 3 records with a year; 1 without are left out
Figure 2

Who is building in Hendricks

Data center developers by MW on record. Top 2 of 2.

Vantage Data Centers 400 MW 3 sites
Radius Data Centers 24 MW 1 site
View as table
DeveloperSitesMW
Vantage Data Centers3400
Radius Data Centers124
Members see all 2 developers, each campus they own here, and the people who run their site selection and energy procurement.
Aggregates only. Campus names are for members.

Power generation in the county

18 plants operate inside Hendricks County, 22.8 MW. Nothing is in the queue for the county.

Figure 3

Operating and planned generation by technology

MW in Hendricks County

OperatingPlanned
Natural GasOperating 9.6 MW 12 projects
SolarOperating 7 MW 1 project
Landfill GasOperating 3.2 MW 2 projects
OilOperating 3 MW 3 projects
View as table
TechnologyStatusProjectsMW
Natural GasOperating129.6
SolarOperating17
Landfill GasOperating23.2
OilOperating33
Operating: 22.8 MW. Planned: 0 MW. Even if every planned project is built, county generation would reach 22.8 MW against 424 MW of data centers.
Source: ISO queues and EIA-860M, via FieldProspects

Hendricks County against its neighbors

Morgan County has the most data center MW among the neighbors, 1.2 GW, more than Hendricks County. 2 of the 3 have more generation operating than data center MW on record.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
Morgan County 6
1,200
644
264 1.9x
Hendricks County this page 4
424
23
0 18.6x
Marion County 7
404
1,513
280 0.27x
Montgomery County 0
0
28
16 0x

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

4 counties shown

Every record in Hendricks County

Campus or project name, developer, status, MW, year and the developer’s contacts, for all 22 records. Filter, sort and export to Excel.

Members only
County: Hendricks County, INStatus: all except cancelledSort: MW, largest first 22 records
Project or campusDeveloperStatusMWYearContacts
22 records and 446.8 MW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Hendricks County

We email you when a data center or power project in Hendricks County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Hendricks County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.