Clark County, Indiana
Clark County, Indiana has 200 MW of data centers on record, planned to operating, across 2 records, against 6.1 MW of generation operating inside the county. The queue adds 600 MW of planned generation across 3 projects, 1 of them past its listed in-service date.
Clark County and its neighbors
Counties shaded by data center MW on record, planned to operating. 1 of its 4 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
more data center MW than operating generation in the county. Clark County's own plants cover 3.1% of the load on record, and the planned pipeline adds 600 MW.
Data centers by status
2 records, 200 MW
The data center pipeline
2 records list a year online or expected, from 2026 to 2026. The largest expected additions are 200 MW listed for 2026.
Data center MW by year online or expected
Records not cancelled, by listed year. 2026 onward is planned or under construction.
View as table
| Year | Records | MW |
|---|---|---|
| 2026 | 2 | 200 |
Who is building in Clark
Data center developers by MW on record. Top 1 of 1.
View as table
| Developer | Sites | MW |
|---|---|---|
| Meta | 2 | 200 |
Power generation in the county
2 plants operate inside Clark County, 6.1 MW of solar and battery storage. The queue adds 600 MW across 3 projects, and one of them is past its listed in-service date.
Operating and planned generation by technology
MW in Clark County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Solar | Operating | 1 | 1.1 |
| Solar | Planned | 2 | 400 |
| Battery Storage | Operating | 1 | 5 |
| Battery Storage | Planned | 1 | 200 |
Planned generation by listed in-service year
MW. Years before 2026 are past due.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2025 | 1 | 200 |
| 2026 | 1 | 200 |
| 2027 | 0 | 0 |
| 2028 | 0 | 0 |
| 2029 | 1 | 200 |
Clark County against its neighbors
None of the 1 neighboring county with a page lists a data center record. Jefferson County has the most operating generation among them, 1.3 GW.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| Clark County this page | 2 | 600 | 32.8x | ||
| Jefferson County | 10 | 0 | 0x |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
2 counties shownEvery record in Clark County
Campus or project name, developer, status, MW, year and the developer’s contacts, for all 7 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for Clark County
We email you when a data center or power project in Clark County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.
Open every campus, project and contact in Clark County.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.