Grundy County, Illinois

Grundy County, Illinois has 2.4 GW of data centers on record, planned to operating, across 11 records, against 3.5 GW of generation operating inside the county. The queue adds 361 MW of planned generation across 16 projects, 1 of them past its listed in-service date.

Data as of Grid region: PJM InterconnectionRefreshed monthly
2.4GW
data centers, planned to operating
11
data center records, not cancelled
21%
of Illinois's data center MW
3.5GW
operating generation, 14 projects
361MW
planned generation, 16 projects
3
data center developers active here
Map

Grundy County and its neighbors

Counties shaded by data center MW on record, planned to operating. 5 of its 5 neighboring counties have pages of their own. The rest are in the member database.

Kendall 2.4 GW LaSalle no data centers Grundy 2.4 GW Kankakee no data centers Livingston no data centers Will 2.1 GW
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
67%

of the generation operating in the county is matched by data center MW on record: 2.4 GW of data centers against 3.5 GW of plants, with 361 MW more planned.

Data centers, planned to operating2.4 GW
Operating generation3.5 GW
Planned generation361 MW

Data centers by status

11 records, 2.4 GW

Planned2.4 GW11 records, 100%
Who owns each of the 11 records?Campus names, developers and contacts are for members.See what members get

The data center pipeline

9 records list a year online or expected, from 2029 to 2033. The largest expected additions are 230.4 MW listed for 2033 and 172.8 MW for 2029. 2 records list no year.

Figure 1

Data center MW by year online or expected

Records not cancelled, by listed year. 2026 onward is planned or under construction.

Through 20252026 and later
0100200300 173 2029 173 2030 2031 2032 230 2033
View as table
YearRecordsMW
20292173
20302173
20312173
20321115
20332230
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026. 9 records with a year; 2 without are left out
Figure 2

Who is building in Grundy

Data center developers by MW on record. Top 3 of 3.

Tract 1 GW 1 site
Aligned 864 MW 9 sites
Cielo Digital Infrastructure 500 MW 1 site
View as table
DeveloperSitesMW
Tract11,000
Aligned9864
Cielo Digital Infrastructure1500
Members see all 3 developers, each campus they own here, and the people who run their site selection and energy procurement.
Aggregates only. Campus names are for members.

Power generation in the county

14 plants operate inside Grundy County, 3.5 GW. The queue adds 361 MW across 16 projects, and one of them is past its listed in-service date.

Figure 3

Operating and planned generation by technology

MW in Grundy County

OperatingPlanned
NuclearOperating 2 GW 2 projects
Natural GasOperating 1.5 GW 6 projects
Solar + Storage (Hybrid)Planned 220 MW 2 projects
SolarOperating 10.9 MW 6 projects
SolarPlanned 131 MW 4 projects
HydroPlanned 10 MW 10 projects
View as table
TechnologyStatusProjectsMW
NuclearOperating22,018.6
Natural GasOperating61,518.8
Solar + Storage (Hybrid)Planned2220
SolarOperating610.9
SolarPlanned4131
HydroPlanned1010
Operating: 3.5 GW. Planned: 361 MW. Even if every planned project is built, county generation would reach 3.9 GW against 2.4 GW of data centers.
Source: ISO queues and EIA-860M, via FieldProspects
Figure 4

Planned generation by listed in-service year

MW. Years before 2026 are past due. 1 planned project lists no date and is left out.

Past dueDue 2026 or later
050100150 Snapshot year 110 2023 2024 2025 131 2026 2027 2028 2029 10 2030
View as table
YearPlanned projectsMW
20231110
202400
202500
20264131
202700
202800
202900
20301010
1 project, 110 MW, was due before 2026

Grundy County against its neighbors

Kendall County has the most data center MW among the neighbors, 2.4 GW, more than Grundy County. 4 of the 5 have more generation operating than data center MW on record.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
Kendall County 4
2,400
1,266
960 1.9x
Grundy County this page 11
2,364
3,548
361 0.67x
Will County 25
2,100
8,089
7,266 0.26x
LaSalle County 0
0
2,824
4,642 0x
Livingston County 0
0
915
1,811 0x
Kankakee County 0
0
248
2,064 0x

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

6 counties shown

What changed since June 4, 2026

9 projects in Grundy County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.

Open the change feed
1
added to a queue, 5 MW
3
came online, started construction or signed an interconnection agreement, 1.3 GW
4
cancelled, dropped or went inactive, 820.1 MW
1
slipped its in-service date, 116 MW

Every change in Grundy County

Project, what changed, technology, MW and the dates that moved, for all 9 changes.

Members only
County: Grundy County, ILSince June 4, 2026 9 changes
ProjectChangeTechnologyMWPrevious dateNew date
9 changes behind this preview

Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.

Request access

Every record in Grundy County

Campus or project name, developer, status, MW, year and the developer’s contacts, for all 41 records. Filter, sort and export to Excel.

Members only
County: Grundy County, ILStatus: all except cancelledSort: MW, largest first 41 records
Project or campusDeveloperStatusMWYearContacts
41 records and 6.3 GW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Grundy County

We email you when a data center or power project in Grundy County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Grundy County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.