Early County, Georgia
Early County, Georgia has 1.4 GW of data centers on record, planned to operating, across 1 record, against 194 MW of generation operating inside the county. Nothing is in the interconnection queue for the county. That is 7.2% of Georgia's data center MW.
Early County and its neighbors
Counties shaded by data center MW on record, planned to operating. 1 of its 5 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
more data center MW than operating generation in the county. Early County's own plants cover 13.9% of the load on record, and nothing is in the queue.
Data centers by status
1 record, 1.4 GW
The data center pipeline
None of the 1 record lists a year online or expected, so the pipeline is shown by developer only.
Who is building in Early
Data center developers by MW on record. Top 1 of 1.
View as table
| Developer | Sites | MW |
|---|---|---|
| QTS | 1 | 1,400 |
Power generation in the county
4 plants operate inside Early County, 194 MW of solar. Nothing is in the queue for the county.
Operating and planned generation by technology
MW in Early County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Solar | Operating | 4 | 194 |
Early County against its neighbors
None of the 1 neighboring county with a page lists a data center record. Clay County has the most operating generation among them, 274 MW.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| Early County this page | 1 | 0 | 7.2x | ||
| Clay County | 0 | 0 | 0x |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
2 counties shownEvery record in Early County
Campus or project name, developer, status, MW, year and the developer’s contacts, for all 5 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for Early County
We email you when a data center or power project in Early County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.
Open every campus, project and contact in Early County.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.