Storey County, Nevada
Storey County, Nevada has 6.7 GW of data centers on record, planned to operating, across 39 records, against 1.2 GW of generation operating inside the county. The queue adds 1 MW of planned generation across 1 project. That is 78.3% of Nevada's data center MW.
Storey County and its neighbors
Counties shaded by data center MW on record, planned to operating. 2 of its 2 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
more data center MW than operating generation in the county. Storey County's own plants cover 17.4% of the load on record, and the planned pipeline adds 1 MW.
Data centers by status
39 records, 6.7 GW
The data center pipeline
37 records list a year online or expected, from 2017 to 2030. The largest expected additions are 859.1 MW listed for 2028 and 695.6 MW for 2027. 2 records list no year.
Data center MW by year online or expected
Records not cancelled, by listed year. 2026 onward is planned or under construction.
View as table
| Year | Records | MW |
|---|---|---|
| 2017 | 1 | 130 |
| 2018 | 0 | 0 |
| 2019 | 0 | 0 |
| 2020 | 0 | 0 |
| 2021 | 1 | 101 |
| 2022 | 0 | 0 |
| 2023 | 0 | 0 |
| 2024 | 1 | 55 |
| 2025 | 2 | 160 |
| 2026 | 7 | 567 |
| 2027 | 5 | 696 |
| 2028 | 10 | 859 |
| 2029 | 5 | 300 |
| 2030 | 5 | 367 |
Who is building in Storey
Data center developers by MW on record. Top 6 of 10.
View as table
| Developer | Sites | MW |
|---|---|---|
| Tract | 2 | 3,485 |
| Amazon | 12 | 900 |
| Switch | 7 | 755 |
| 4 | 549 | |
| Fleet Data Centers | 4 | 460 |
| Vantage Data Centers | 4 | 291 |
Power generation in the county
30 plants operate inside Storey County, 1.2 GW. The queue adds 1 MW across 1 project.
Operating and planned generation by technology
MW in Storey County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Natural Gas | Operating | 22 | 1,150.5 |
| Battery Storage | Operating | 1 | 10 |
| Solar | Operating | 7 | 7.7 |
| Solar | Planned | 1 | 1 |
Planned generation by listed in-service year
MW. Years before 2026 are past due.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2026 | 1 | 1 |
Storey County against its neighbors
Lyon County has the most data center MW among the neighbors, 700 MW, 10% of Storey County's. 1 of the 2 have more generation operating than data center MW on record.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| Storey County this page | 39 | 1 | 5.8x | ||
| Lyon County | 3 | 1,400 | 2.5x | ||
| Washoe County | 12 | 0 | 0.17x |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
3 counties shownWhat changed since June 4, 2026
1 project in Storey County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.
Every change in Storey County
Project, what changed, technology, MW and the dates that moved, for all 1 change.
| Project | Change | Technology | MW | Previous date | New date |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.
Every record in Storey County
Campus or project name, developer, status, MW, year and the developer’s contacts, for all 70 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for Storey County
We email you when a data center or power project in Storey County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.
Open every campus, project and contact in Storey County.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.