Suffolk County, Massachusetts

Suffolk County, Massachusetts has 20.1 MW of data centers on record, planned to operating, across 3 records, against 268.9 MW of generation operating inside the county. The queue adds 800 MW of planned generation across 3 projects. That is 34.6% of Massachusetts's data center MW.

Data as of Grid region: ISO New EnglandRefreshed monthly
20.1MW
data centers, planned to operating
3
data center records, not cancelled
34.6%
of Massachusetts's data center MW
268.9MW
operating generation, 48 projects
800MW
planned generation, 3 projects
3
data center developers active here
Map

Suffolk County and its neighbors

Counties shaded by data center MW on record, planned to operating. 3 of its 3 neighboring counties have pages of their own. The rest are in the member database.

Suffolk 20.1 MW Norfolk no data centers Essex 5 MW Middlesex 29 MW
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
7%

of the generation operating in the county is matched by data center MW on record: 20.1 MW of data centers against 268.9 MW of plants, with 800 MW more planned.

Data centers, planned to operating20.1 MW
Operating generation268.9 MW
Planned generation800 MW

Data centers by status

3 records, 20.1 MW

Operating20.1 MW3 records, 100%
Who owns each of the 3 records?Campus names, developers and contacts are for members.See what members get

The data center pipeline

None of the 3 records lists a year online or expected, so the pipeline is shown by developer only.

Figure 1

Who is building in Suffolk

Data center developers by MW on record. Top 3 of 3.

Centersquare (formerly Evoque) 16 MW 1 site
EdgeConneX 2.6 MW 1 site
DataBank 1.5 MW 1 site
View as table
DeveloperSitesMW
Centersquare (formerly Evoque)116
EdgeConneX13
DataBank12
Members see all 3 developers, each campus they own here, and the people who run their site selection and energy procurement.
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026. Aggregates only. Campus names are for members.

Power generation in the county

48 plants operate inside Suffolk County, 268.9 MW. The queue adds 800 MW across 3 projects.

Figure 3

Operating and planned generation by technology

MW in Suffolk County

OperatingPlanned
Battery StorageOperating 1.5 MW 2 projects
Battery StoragePlanned 800 MW 3 projects
OilOperating 165.4 MW 27 projects
Natural GasOperating 75 MW 8 projects
BiomassOperating 17.5 MW 1 project
SolarOperating 4.8 MW 5 projects
WindOperating 2.7 MW 3 projects
HydroOperating 2 MW 2 projects
View as table
TechnologyStatusProjectsMW
Battery StorageOperating21.5
Battery StoragePlanned3800
OilOperating27165.4
Natural GasOperating875
BiomassOperating117.5
SolarOperating54.8
WindOperating32.7
HydroOperating22
Operating: 268.9 MW. Planned: 800 MW. Even if every planned project is built, county generation would reach 1.1 GW against 20.1 MW of data centers.
Source: ISO queues and EIA-860M, via FieldProspects
Figure 4

Planned generation by listed in-service year

MW. Years before 2026 are past due.

Past dueDue 2026 or later
0200400600 500 2027 300 2028
View as table
YearPlanned projectsMW
20272500
20281300
No planned project is past its listed year

Suffolk County against its neighbors

Middlesex County has the most data center MW among the neighbors, 29 MW, more than Suffolk County. 3 of the 3 have more generation operating than data center MW on record.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
Middlesex County 2
29
476
1,729 0.06x
Suffolk County this page 3
20
269
800 0.07x
Essex County 1
5
1,154
430 0x
Norfolk County 0
0
2,741
781 0x

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

4 counties shown

What changed since June 4, 2026

1 project in Suffolk County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.

Open the change feed
0
added to a queue, 0 MW
0
came online, started construction or signed an interconnection agreement, 0 MW
0
cancelled, dropped or went inactive, 0 MW
1
slipped its in-service date, 250 MW

Every change in Suffolk County

Project, what changed, technology, MW and the dates that moved, for all 1 change.

Members only
County: Suffolk County, MASince June 4, 2026 1 change
ProjectChangeTechnologyMWPrevious dateNew date
1 change behind this preview

Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.

Request access

Every record in Suffolk County

Campus or project name, developer, status, MW, year and the developer’s contacts, for all 54 records. Filter, sort and export to Excel.

Members only
County: Suffolk County, MAStatus: all except cancelledSort: MW, largest first 54 records
Project or campusDeveloperStatusMWYearContacts
54 records and 1.1 GW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Suffolk County

We email you when a data center or power project in Suffolk County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Suffolk County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.